SECTION 02082
the Commissioner. Prior to starting the work at any site; specify clearly the
temporary locations of facilities preferably with sketches and submit the same to
the Resident Engineer and Construction Manager for approval.
2. Water:
a. The Department of Design and Construction will furnish all water needed for
construction, at no cost to the Contractor in buildings under their jurisdiction. All
temporary plumbing or adaptations to supply the needs of the Work Area shall be
performed and removed by the Contractor and the cost thereof included in the
Lump Sum price Bid for abatement work. Shower water for the decontamination
unit shall be provided hot. Heating of water, if necessary, shall be provided by
the Contractor.
3. Electricity:
The Department of Design and Construction will furnish all electricity needed for
construction, at no cost to the Contractor in buildings under their jurisdiction. All
temporary electrical work or adaptations to supply the needs of the Work Area
shall be installed and removed by the Contractor and the cost thereof included in
the Lump Sum price Bid for abatement work.
All temporary lighting and temporary electrical serx ices for use in the Work Area
shall be in weather proof enclosures and be ground fault protected and:
(1) Shall be performed at no additional charge to the City.
(2) Shall be performed at times not interfering with the other activities in the
building.
E. Contractor shall provide a separate temporary electric panel board to power Contractor’s
equipment. The Facility and Construction Manager will designate an existing electrical source in
proximity to the Work Area. Contractor's licensed electrician shall provide temporary tie-in via
cable, outlet boxes, junction boxes, receptacles and lights, all with ground fault interruption. At
no time shall extension cords greater than 50-feet in length be allowed. All temporary electrical
installation shall be in accordance with OSHA regulations. The electric shut down for power
panel tie-in will be on off-hours and must be coordinated with the Facility and Construction
Manager. The Contractor shall provide to the Conslruction Manager a specification and drawing
outlining his power requirements at the pre-construction meeting.
F. Additional electrical equipment (i.e. transformers, etc.), which is necessary due to the lack of
existing power on the floor shall be at the Contractor's expense.
G. Contractor shall provide fire protection in accordance with all State and Local fire codes.
H. When temporary service lines are no longer required, they shall be removed by the Contractor.
Any parts of the permanent service lines, grounds and buildings, disturbed or damaged by the
installation and/or removal of the temporary service lines, shall be restored to their original