NYC 9/11 Public Portal Document
SECTION 02082
condition by the Contractor. Senior Stationary Engineer will inspect and test all switches,
controls, gauges, etc. and shall submit a list to the Resident Engineer and Construction Manager
of any equipment damaged by the Contractor.
I. Contractor shall supply hot shower water necessary for use in the contamination unit.
1.23 USE OF THE PREMISES
A. Contractor shall confine his apparatus, the storage of materials, and supplies, and the operation
of his workmen to limits established by law, ordinances, and the directions of the Resident
Engineer, Construction Manager and the Facility. All flammable or combustible materials shall
be properly stored to obviate fire and in areas approved by the Facility.
B. Contractor shall assure that no exits from the building are obstructed, that appropriate safety
barriers are established to prevent access, and that Work Areas are kept neat, clean, and safe.
C. All surrounding work, fixtures, soil lines, drains, water lines, gas pipes, electrical conduit, wires,
utilities, duct work railings, shrubbery, landscaping, etc. which are to remain in place shall be
carefully protected and, if disturbed or damaged, shall be repaired or replaced as directed by the
City, at no additional cost.
D. All routes through the building to be used by the Contractor shall first be approved by the
Resident Engineer, Construction Manager and the Facility.
E. Attention is specifically drawn to the fact that other Contractors, performing the work of other
Contracts, may be (or are) brought upon any of the work sites of this Contract. Therefore, the
Contractor shall not have exclusive rights to any site of his work and shall fully cooperate and
coordinate his work with the work of other Contractors who may be on (or are on) any site of the
work of this Contract. Regulated area excepted.
F. Temporary toilet facilities must be provided by the Contractor on the site. Coordinate location of
facilities with the Construction Manager and Resident Engineer. No toilet facilities will be
allowed in the Work Area.
1.24 RESPIRATORY PROTECTION REQUIREMENTS
A. Respiratory protection shall be worn by all individuals who may be exposed to asbestos fibers
from the initiation of the asbestos project until all areas have successfully passed clearance air
monitoring in accordance with Regulations and these Specifications.
B. Contractor shall develop and implement a written respiratory protection program with required
site-specific procedures and elements. The program shall be administered by a properly trained
individual. The written respiratory protection program shall include the requirements set forth in
OSHA Standard 29 CFR 1910.134, at a minimum.
C. The Contractor shall provide workers with individually issued and marked respiratory
equipment. Respiratory equipment shall be suitable for the asbestos exposure level(s) in the
Work Area(s), as specified in OSHA Standards 29 CFR 1910.134 and 29 CFR 1926.1101,
02082-35
CITY_21 MCI 00_014563808
NYC-WTC_000454608
OCR can misread numbers and units. Confirm readings against the page image before using them.