Asbestos Abatement
on-center.
(2) When worker decontamination unit is located outdoors, in
areas with public access, or in correctional facilities, frame
work shall be lined with minimum 3/8" thickness plywood
sheathing. Sheathing shall be caulked or taped airtight at all
joints and seams.
(3) Interior shall be covered with two layers of opaque 6-mil
polyethylene sheeting, with a minimum overlap of 16
inches at seams. Seal seams airtight using tape and
adhesive. The interior floor shall be covered with two (2)
layers of reinforced fire-retardant polyethylene sheeting
with a minimum overlap on the walls of sixteen inches.
(4) Entrances to the decontamination unit shall be secured with
lockable hinged doors. Doors shall be open at all times
when abatement operations are in progress. Doors shall be
louvered to allow for air movement through the
decontamination units into Work Area.
b) Curtained Doorways: A device to allow ingress or egress from one
room to another while permitting minimal air movement between
the rooms.
c) Air Locks: Air locks shall consist of two curtained doorways
placed a minimum of three feet apart.
d) Decontamination Enclosure System shall be placed adjacent to the
Work Area and shall consist of three totally enclosed chambers,
separated from Work Area and each other by airlocks, as follows:
(1) Equipment Room: The equipment room shall have a curtain
doorway to separate it from the Work Area, and share a
common airlock with the shower room. The equipment
room shall be large enough to accommodate at least one
worker (allowing them enough room to remove their
protective clothing and footwear), and a 6-mil disposal bag
for collection of discarded clothing and equipment. The
equipment room shall be utilized for the storage of
equipment and tools after decontamination using a HEPA-
vacuum and/or wet cleaning. A one-day supply of
replacement filters, in sealed containers, for HEPA-
vacuums and negative air machines, extra tools, containers
of surfactant, and other materials and equipment required
for the project shall be stored here. A walk-off pan filled
CAPITAL PROJECT NUMBER PO79201K 02081-55
100: CONTRACT DOCUMENTS REV. May 3,2000
- 55 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631304
NYC-WTC_000416816