NYC 9/11 Public Portal Document
Asbestos Inspection Report
Premise No. Inspection Date:
130 Liberty Street 02/16/09
Eloor Zip Borough Block Lot Squad # Badge #
Various_________ 10006 1 54 1 1 A062
Inspector Building Type Basis of Inspection Photos Taken
M.Gagnidze F TRU2068MN08 yes
Contractor’s Name Sample Number
LVI Environmental
Address City Sample Number
State Zip Phone Sample Number
Laboratory Name Owner's Name
TRC Environmental Corp The Lower Manhattan Development Corp.
Address City Address City
1340 Broadway New York One Liberty Plaza New York
State Zip Phone State Zip Phone
NY 10018 NY 10006 (212) 962-2300
Contact Person Time of Inspection from:
Arnel Javal, Sr. Proj. Mgr/TRC Environmental 9:00 am to 10:30 am
I arrived at the premise at 9:00 am, proceeded to the decon, signed the log book, don the appropriate level of
personal protective equipment to enter the regulated area on 8“' floor.
8‘''Floor - 7 workers were present at the North vestibule, jack hammering the floor using crow bar with HEPA
vacuum attached to remove walker ducts, fine spraying with amended water has been performed; two other
workers were picking up debris, placing into the black asbestos waste bags. One micro trap machine was
powered on and 1 on stand by. After following the decontamination procedure I signed the log book and used
south hoist to go to the 4"' floor.l proceeded to the decon, signed the log book, don the appropriate level of
personal protective equipment to enter the regulated area. Negative air pressure on the floor was 0.032. One
worker was present for the decon maintenance.
4"' Floor - 25 workers were present on the floor, washing, sweeping and vacuuming the floor with equipment
equipped with HEPA filters, fine cleaning horizontal and vertical surfaces at the spandular beams, critical
barriers, at the south side of the work area, re-sealing the critical barriers, replacing the filters, clearing off the
floor, preparing for the visual inspection. I observed that 1 light bulb protection was open. I took the picture and
advised Handler Supervisor, who directed Platinum Electrician worker to repair the cage in concern. 3 Gaylord
boxes were ready to be taken out. I used B stairs to proceed to the 3'Yloor
3’'“ Floor - 28 workers were working on the floor. Workers on the scissor lift were in the process of removing air
ducts, beams, using hammer and power tools, attached to the HEPA vacuum, taking down the drop ceiling at
the east side of the area, removing metals from the ceiling at the east side vestibule, cutting metal using the
tools with HEPA vacuum attached, demolishing the wall between two shafts, cutting pipes on the floor at the
north/west side vestibule. Others were loading out boxes and poly wrapped beams, which has been sprayed
with amended water, picking up debris, preparing boxes. 15 Gaylord boxes were ready to be taken out.
Inspection was done on micro trap machines and tents. I used B stairwell to proceed to the 2"'’ floor.
2"” Floor - 53 workers were found inside the work place. Workers on scaffolds at the east side of the area
were removing metal fixtures from the ceiling at the various locations of the floor, cutting metal into the pieces,
using power tool with HEPA vacuum attached, spraying the area with amended water, demolishing the air duct,
removing metal ceiling components; carpenters working with wood erecting platforms at the east side of the
work area. Other workers were picking up debris from the floor, placing into the boxes and spraying with
amended water, wrapping beams with poly, preparing boxes. 22 Gaylord boxes were on the floor sealed,
sprayed and ready for load out, 35 micro trap machines were powered on and 5 on stand by. Inspection was
done on micro trap tents. I used B stairwell to proceed to the floor.
V Floor - 34 workers were clearing off the floor. A large amount of debris and poly wrapped beams exists on
the floor. Workers at the east side of the work area were cutting air ducts, demolishing the wall at the north
side, cutting debris and placing into the boxes, spraying the work areas with amended water, replacing the
filters of micro trap machines, preparing, wrapping and loading out boxes through the waste decon, 10 sealed
and 7 open Gaylord boxes were on the floor. I observed that debris into two Gaylord boxes were dry. Handlers
Supervisor was advised, who directed workers to wet the debris and boxes with amended water before taking
them out. I used B stairwell to proceed to the 4'" floor. After following the decontamination procedure I signed
the log book and used south hoist to return to the ground floor. Inspection was done on ATC trailer.
NOV# Infraction Infraction Infraction Infraction
NOV# Infraction Infraction Infraction Result Code
2
NOV# Infraction Infraction Infraction Supervisor’s Initial
Borough I “Manhattan 2=Bronx 3=Brooklyn 4=Queens 5=Richmond
Building Type A >6 stories B <6 stories C single family D school E hospital F public owned
Result Code I = Violation Issued 2=No Violation Issued 3=No access 4=Project not started (no NOV)
5=Public Owned Property
CITY_DEP_WORBY_CANNATA_SUBP_000131201
NYC-WTC_000182033