NYC 9/11 Public Portal Document
Asbestos Inspection Report
Premise No, Inspection Date:
130 Liberty Street 02/11/09
Floor ■ Zip Borough Block Lot Squad # Badge #
Various 10006 1 54 1 1 A062
Inspector Building Type Basis of Inspection Photos Taken
M.Gagnidze F TRU2068MN08 yes
Contractor's Name Sample Number
LVI Environmental
Address City Sample Number
State Zip Phone Sample Number
Laboratory Name Owner's Name
TRC Environmental Corp The Lower Manhattan Development Corp,
Address City Address City
1340 Broadway New York One Liberty Plaza New York
State Zip Phone State Zip Phone
NY 10018 NY 10006 (212) 962-2300
Contact Person Time of Inspection from:
Arnel Javal, Sr, Proj. Mgr/TRC Environmental 8:45 am to 10:45 am
I arrived at the premise at 8:45 am, proceeded to the decon, signed the log book, don the appropriate level of
personal protective equipment to enter the regulated area on 5'^ floor. Negative air pressure on the floor was
0.034, One worker was present for the decon maintenance, cleaning the clean room and shower chamber.
5*” Floor - 18 workers were present on the floor, fine cleaning, re-sealing the critical barriers, platforms at the
shaft area, walls at the North side, re-sealing the door of the electrical room, repairing 2 light bulb cages; two
workers were cleaning and re-plasticizing the mezzanine on the North side. 2 Gaylord boxes were ready for
load out and 1 box was still open. Inspection was done on micro trap machines and tents.
After following the decontamination procedure I signed the log book and used north hoist to go to the 3'^ floor.
I proceeded to the decon, signed the log book, don the appropriate level of personal protective equipment to
enter the regulated area on 3^ floor. Negative air pressure on the floor was 0.018.
3''^' Floor - 32 workers were working on the floor, demolishing the shaft on the west side and the wall on the
east side of the work area, Eagle working on erecting platforms in shaft area, removing metal fixtures from the
ceiling, replacing the filters of micro trap machines, picking up debris, placing into the boxes and spraying with
amended water, wrapping beams with poly. 10 Gaylord boxes were ready for load out. Inspection was done on
micro trap machines and tents. I used B stairwell to proceed to the 4’^ floor.
4“’ Floor - 12 workers were present on the floor, washing wall, ceiling and beams on the north side of the area,
sealing critical barriers on the south side, resealing the door of the electrical room, washing equipment,
replacing the filters, clearing off the floor. I observed that 2 light bulb cages were open and 1 bulb was without
protection. I took the pictures and advised Handler Supervisor, who directed Platinum Electrician to repair the
cages in concern. 2 Gaylord boxes were ready to be taken out, I used B stairs to proceed to the 2’'“ floor,
2"’Floor - 42 workers were found inside the work place. Workers on scaffolds at the west side of the area
were removing metal fixtures from the ceiling, cutting metal into the pieces, using power tool with HEPA
vacuum attached, spraying the area with amended water, carpenters working with wood setting up platforms.
Other workers were picking up debris from the floor, placing into the boxes and spraying with amended water,
wrapping beams with poly, preparing boxes. 4 sealed and 8 open Gaylord boxes were on the floor. 35 micro
trap machines were powered on and 5 on stand by. I observed that 1 micro trap was without a power and 1
light bulb was without protection. Handler Supervisor was advised and he directed workers to inspect the micro
trap and set up the light bulb cage. Inspection was done on micro trap tents.
I used B stairwell to proceed to the V floor.
V Floor - 40 workers were clearing off the floor. A large amount of debris and poly wrapped beams exists on
the floor. Workers at the east and north side of the work area were demolishing the sheetrock wall, placing
debris into the boxes, spraying boxes and work areas with amended water, preparing, wrapping and loading
out boxes through the waste decon, replacing the filters of micro trap machines. 28 sealed and 15 open
Gaylord boxes were on the floor. 40 micro trap machines were powered on and 5 on stand by. Inspection was
done on micro trap tents. After following the decontamination procedure I signed the log book and used north
hoist to return to the ground floor. Inspection was done on ATC trailer.
NOV# Infraction Infraction Infraction Infraction
NOV# Infraction Infraction Infraction Result Code
2
NOV# Infraction Infraction Infraction Supervisor’s Initial
Borough l=Manhattan 2=Bronx 3=Brooklyn 4=Queens 5=Richmond
Building Type A >6 stories B <6 stories C single family D school E hospital F public owned
Result Code 1 = Violation Issued 2=No Violation Issued 3=No access 4^Project not started (no NOV)
5=Public Owned Property
CITY_DEP_WORBY_CANNATA_SUBP_000131195
NYC-WTC_000182030
OCR can misread numbers and units. Confirm readings against the page image before using them.