Asbestos inspection log, 130 Liberty Street, February 11, 2009

Machine-extracted title · confidence 95%

Record of an asbestos inspection conducted at 130 Liberty Street on February 11, 2009, by TRC Environmental Corp.

NYC-WTC_000182031
Page image
Scanned page image, NYC-WTC_000182031
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Asbestos Inspection Report

Premise No. Inspection Date: _130 Liberty Street 02/11/09 Floor Zip Borough Block Lot Squad # Badge # Various_________ 10006 1 54 1 1 A062 Inspector Building Type Basis of Inspection Photos Taken M.Gagnidze_____ F TRU2Q68MN08 yes Contractor's Name Sample Number LVI Environmental Address City Sample Number

State Zip Phone Sample Number

Laboratory Name Owner's Name TRC Environmental Corp The Lower Manhattan Development Corp. Address City Address City 1340 Broadway New York One Liberty Plaza New York State Zip Phone State Zip Phone NY 10018 NY 10006 (212) 962-2300 Contact Person Time of Inspection from: Arnel Javal, Sr. Proj. Mgr/TRC Environmental 1:55 pm to 3:00 pm I arrived at the premise at 1:55 pm. LVI schedule informed that activities include clear off floor, do scrape visuals on 4*'’ floor, demo in shafts, demo walls, clear off floor, temp platforms in shaft on 3'^'’ floor, demo walls & ducts, clear off floor, erect platform East side on 2"“ floor, clear floor, cut ducts, demo walls, prep East side arcade walls on 1®' floor. I proceeded to the decon, signed the log book, don the appropriate level of personal protective equipment to enter the regulated area on S'^floor. Negative air pressure on the floor was 0.023. One worker was present for the decon maintenance, cleaning the clean room. Using B stairwell I proceeded to the 4"Tloor. 4"’ Floor - 12 workers were present on site. Workers on 2 scaffolds on North side of the work area were washing the ceiling, beams and columns with amended water, others were re-sealing the critical barriers on the South side, clearing off the floor, 3 light bulbs were still with open cages. Handler Supervisor claimed that he was waiting for the electricians to repair the light bulb protections. 3 Gaylo9rd boxes were sealed and sprayed with amended water. Inspection was done on micro trap machines and tents. Using B stairwell I proceeded to the 3"^ floor. 3’ '' Floor - 32 workers were working on the floor. Workers on scissor lift were demolishing the sheetrock wall at the area between the shafts, setting up the platforms inside the shaft area, removing metals from the frame at the top of the critical barriers on the west side of the floor, cutting metal into the pieces using power tools with HEPA filters attached, others were wrapping debris with poly, preparing and loading out boxes. 20 Gaylord boxes were on the floor ready for load out. 30 micro trap machines were powered on and 5 on stand by Inspection was done on micro trap tents. I used B stairwell to proceed to the 2"'’ floor. 2"“ Floor - 42 workers were found inside the work place. Workers on scaffolds cutting and removing air duct on the west side of the floor, removing metal fixtures from the ceiling, cutting metal into the pieces using tools with HEPPA vacuum attached, spraying around the area with amended water. Eagle scaffolding workers were erecting the platforms on the East side of the work area. Other workers were picking up debris from the floor, placing into the boxes and spraying, wrapping beams with poly, preparing boxes. 12 Gaylord boxes and a large amount of poly wrapped beams were ready to be taken out. 25 micro trap machines were powered on and 5 on stand by. Inspection was done on micro trap tents. I used B stairwell to proceed to the V floor. 1®' Floor - 40 workers were clearing off the floor. A large amount of debris still exists on the floor. Workers at the north side area were cutting and removing the air duct, cutting metals at the various locations on the floor, placing debris into the boxes, spraying boxes and work areas with amended water, plasticizing the frames of the engine machine with poly inside the electrical room, preparing, wrapping and loading out boxes through the waste decon. 15 sealed Gaylord boxes were on the floor. 35 micro trap machines were powered on and 5 on stand by. Inspection was done on micro trap tents. After following the decontamination procedure I signed the log book and left the remote decon, located on the ground floor. Inspection was done on ATC trailer.

NOV# Infraction Infraction Infraction Infraction

NOV# Infraction Infraction Infraction Result Code 2 NOV# Infraction Infraction Infraction Supervisor’s Initial

Borough l=Manhanan 2=Bronx 3=Brooklyn 4=Queens 3=Richmond Building Type A>6storiss B <6 stories C single family D school E hospital F public owned Result Code I = Violation Issued 2=No Violation Issued 3=No access 4=Project not started (no NOV) 5=Public Owned Property

C ITY_D EP_WO RBY_C AN NAT A SU B POO0131196

NYC-WTC_000182031

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000182031Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →