AMBASSADOR CONSTRUCTION CO.. INC.
Mayor’s Office of Emergency Management
7 World Trade Center
May 27, 1998
Page Two...
Breakdown Continued...
Furniture 300,500.00
Audio Visual 1,793,907.00
Fabric Wall Panels 19,800.00
Projection Screen 16,732.00
Folding Wall 17,996.00
Metal Panel Wall 18,000.00
Special Doors 34,630.00
Metal Shelving 11,726.00
Safe Door 4,130.00
Rolling Fire Door 3,384.00
Cut & Patch 30,000,00
Generator Test 4,500.00
Wire Mesh Partition 3,250.00
General Conditions 8% 788,414.00
Overhead & Fee 6% 638,616.00
Insurance 1.25% 141^028.00
Total $11,423,238.00
- Previously approved cost to pre-purchase generator and switch
gear $717,890.00
Qualifications
- Demolition to be performed on week nights
- Use of EMT wiring and rigid conduit for all vertical runs and conduit over 2" diameter
- All furniture devices furnished by vendor
- Furnish and installation of security equipment is based upon Vikonics, Inc.’s drawings and
specifications
- All security wiring to be run in plenum, furnish and installation of conduits is limited to
Drawing TC-101 only
- Installation of cable tray and conduit required in Section 16700
- Furnish and installation of heat trace cable as per the electrical drawings only
- Termination of telephone and data wiring or cabling
- Control system for HVAC equipment not as specified, but as per meeting with Engineer
- (Overtime except where required by building rules --------------------- -
Forward.../