BULLETIN #1 (PORT AUTHORITY COMMENTS)
Description of work Ambassador's Cost
1 Delete concrete and reinforcingfor new oil tank cradle ($19,380.00) ($24,945.00)
2 New 4" concrete housekeeping pad under oil tank $1,500.00 $1,500.00
3 Installation of annunciator panel as per note #16 drawing # E1-23 $0.00 $0.00
4 Furnish and install auxiliary contacts in each circuit breaker
of switch board EDPH-23 $0.00 $0.00
5 Change switch board EDPH-23 from fuse to circuit breaker $0.00 $0.00
Change the interrupting capacity of panel EDPH-23M from 65KA
to 100KA $7,080.00 $3,540.00
7 Fiil additional fire alarm devises as per revised drawing E4-03
dated 7/24/98 $3,205.00 $2,750.00
8 F&l additional circuit breakers to panel EHP-1 and ELP-23W
as directed by the engineer $1,360.00 $1,360.00
9 Upgrade the size of ground conductor to 1#2 in 1 1/4" conduit
as per drawing #E3-01 dated 7/24/98 $3,690.00 $3,690.00
TOTAL ($2,545.00) ($12,105.00)
General conditions 8% -$203.60 -$968.40
Sub-total ($2,748.60) ($13,073.40)
Fee 6% ($164.92) ($784.40)
Sub-total ($2,913.52)1 ($13,857.80)
Insurance 1.25% ($36.42) ■ ($173.22)
GRAND TOTAL ($2,949.93) ($14,031.03)