Window removal quote, 7 World Trade Center, May 1998 · Box 7DCASNYC-WTC_000172774
Quote for removal of windows on 7th and 23rd floors of 7 World Trade Center, totaling $22,700.00.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.975
Change Order #26 submission, 7 WTC, Nov 1998 · Box 7DCASNYC-WTC_000171821
Letter from Ambassador Construction submitting change order #26 for drywall and electrical patching work at the Mayor's Office of Emergency Management.
2 shared non-person entities · Same agency, volume and box · similarity 0.874
Construction cost estimate, 7 WTC OEM, Feb 1998 · Box 7DCASNYC-WTC_000170825
Ambassador Construction submits a $10.8 million cost estimate for demolition and fit-out work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.872
Revised Change Order #26R, drywall and ceilings, 7 WTC, Dec · Box 7DCASNYC-WTC_000168605
Submission of Revised Change Order #26R for drywall closure, scar patching, and ceiling work at 7 World Trade Center.
Same agency, volume and box · similarity 0.869
Change Order #26 for drywall and electrical work, 7 World · Box 7DCASNYC-WTC_000173876
A memo submits Change Order #26 for $12,599 to close door openings, patch ceilings, and modify electrical systems at 7 World Trade Center.
Same agency, volume and box · similarity 0.867
OEM 7th and 23rd floor preliminary construction budget, February 1998 · Box 7DCASNYC-WTC_000167743
Preliminary construction budget of $10,879,098 for tenant interior fit-out work on the 7th and 23rd floors of 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.866
Change Order #048 for access door installation, Jan 1999 · Box 7DCASNYC-WTC_000171862
Submission of change order #048 to furnish and install a new 24x24 access door and hardware at room 23-51.
Same agency, volume and box · similarity 0.864
Change order #025 for roof antenna support, Nov 1998 · Box 7DCASNYC-WTC_000171920
Quotation for structural steel supports and fireproofing required to mount microwave dishes on the World Trade Center roof in November 1998.
Same agency, volume and box · similarity 0.863
Change Order #26R submission, 7 WTC, Dec 1998 · Box 7DCASNYC-WTC_000171810
Letter from Ambassador Construction submitting revised change order #26R for repairs at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.862
Change Order #38 submission for construction work, Dec 1998 · Box 7DCASNYC-WTC_000171840
Letter submitting Change Order #38 for $8,346.00 for unspecified scope of work at the Office of Emergency Management.
1 shared non-person entities · Same agency, volume and box · similarity 0.861
Construction proposal changes, 7 World Trade Center, Jun 1998 · Box 7DCASNYC-WTC_000173021
Letter detailing scope and cost reductions for electrical and audiovisual work at the Mayor's Office of Emergency Management following a review of bid items.
1 shared topics · Same agency, volume and box · similarity 0.861
NYC-WTC_000171626 · Box 7DCAS1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.861