NYC-WTC_000173352
Revised construction proposal for Mayor's Office of Emergency Management work at 7 World Trade Center totaling $11,645,746.
Same agency, volume and box · similarity 0.896
machine-extracted · confidence unavailable · Check page ↗Cover sheet for a fax transmission from Burgess Steel estimating department regarding structural steel work.
NYC-WTC_000172731–000172732Folder label: “Mayor's Office of Emergency Management '7 World Trade Center®New York, NY®BSP Est# 98-05-4295 Rev. 1”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
05/22/1998 11:10 2018718705 BURGESS STEEL PAGE 02
Phone; (201)871-3500 (212)563-6000 EiX: (201)871-8750
BURGESS 200 WEST FOREST AVENUE • P.O. BOX 9880 • ENGLEWOOD. N-1.07631-9880
May 22, 1998
Ambassador Construction 317 Madison Avenue New York, NY 10017
Attention: Mr, Jack Klein Re; Mayor's Office of Emergency Management 7 World Trade Center New York, NY BSP Est# 98-05-4295 Rev.l Gentlemen:
We are pleased to submit our quotation based upon the following drawings: Architectural Drawings: D-0 thru 12, T-1, A-EG-23, Al-1, A7-1, A23-1 thru 6, A48-1 dated 5/4/98 Prepared by Swanke Hayden Connel Structural Drawings; S-1 thru 5 dated 5/4/98 Prepared by Cantor Seinuk
SCOPE 1. Furnish and install steel post, framing and metal deck for fuel tank at .1* floor (straight time) 2. Furnish and install support steel for g inerator, water tank and switch gear at 7“’' floor (overtime) 3, Furnish and install support steel for c lolihg towers at 23'^ floor (overtime) — 4. Furnish and install 1/2" thick steel plate; to top of slab for support of water bottles at ZS”’ floor (straight — time) 5. Furnish and install support steel for 1 siding partition at 23^ floor (overtime) - 6. Furnish and install steel sub-framing posts, flaming, bracing and metal deck for radio room at roof (straight time) — 6 ^>’227^'' 7. Furnish and install steel posts, framing and grating for fuel oil pump at 1“ floor (overtime) 8. Furnish and install approx. 50 If of seismic clip angles (overtime) 9, Furnish and install approx. 80 if of door supports at office and library on 23"' floor (overtime) . 10. Furnish and install support steel for antenna at roof (six locations) (straight time) - ’ II. Furnish and install one steel ladder and Bilco roof scuttle (straight time) 12. Furnish and install support steel for monitors (two locations) (overtime) - 13. Furnish and deliver only loose lintels
AH of the above will be flimished as outlined for the lump sum price of S264.400.00 (Two hundred sixty four thousand four hundred dollars)
EXCLUSIONS 1. Toilet partition supports. 2. Drawing D'3. Work by AV contract )r. 3. Cutting and patching of concrete and masonry. 4. Exposing and cleaning existing struct iral steel for the connection of the new steel. 5. Field paint and touch-up.
NYC-WTC_000172731
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000173352
Revised construction proposal for Mayor's Office of Emergency Management work at 7 World Trade Center totaling $11,645,746.
Same agency, volume and box · similarity 0.896
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171318
Contractor submission of revised change order #44R for fuel oil line supports, enclosures, and new routing at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.896
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168439
Change order for $85,893 covering support structures, concrete encasement, routing, and patching for fuel oil lines and enclosures at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.894
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172028
Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
1 shared topics · Same agency, volume and box · similarity 0.894
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173073
Revised construction proposal from Ambassador Construction for work at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.893
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172600
Letter submitting a revised HVAC quotation totaling $1,564,675 for the Mayor's Office of Emergency Management at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.892
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173453
Letter from Ambassador Construction submitting Change Order #004 for concrete and electrical work at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.892
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172123
Contractor submits a revised proposal totaling $11.6 million for demolition and construction work at 7 WTC.
Same agency, volume and box · similarity 0.892
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172953
Memo dated April 27, 1999 requesting funding from the construction budget for metro traffic feed and dish installation at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.890
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172316
Proposal from Ambassador Construction Company for demolition and construction work at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.890
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173147
A revised construction proposal from Ambassador Construction Co. Inc. for demolition and renovation work on the 1st, 7th, and 23rd floors of 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.890
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000143354
Fragmented text containing only a reference number and unreadable characters from the DEP Box 06 collection.
2 shared non-person entities · 1 shared topics · similarity 0.898
machine-extracted · confidence unavailable · Check page ↗Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000173690
Log of change orders for sheetrock, cooling circuits, and door modifications at the Mayor's Office site.
Similarity score 0.951 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172260
Minutes of the sixteenth consultant meeting detailing construction status and fuel oil piping installation.
Similarity score 0.949 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000166704
Minutes from the 15th consultant meeting at 7 World Trade Center dated October 27, 1998.
Similarity score 0.948 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000166707
Minutes from the 14th consultant meeting at 7 World Trade Center dated October 20, 1998.
Similarity score 0.947 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173725
Summary list of change orders with status and costs for the Mayor's Office of Emergency Management project as of November 4, 1998.
Similarity score 0.947 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172707
Estimate from Ambassador Construction Company for furnishing and installing pumps, steel tanks, and hot water heaters at the Office of Emergency Management.
Similarity score 0.947 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000143354
Fragmented text containing only a reference number and unreadable characters from the DEP Box 06 collection.
Similar indexed content
NYC-WTC_000173352
Revised construction proposal for Mayor's Office of Emergency Management work at 7 World Trade Center totaling $11,645,746.
Similar indexed content
NYC-WTC_000171318
Contractor submission of revised change order #44R for fuel oil line supports, enclosures, and new routing at 7 World Trade Center.
Similar indexed content
NYC-WTC_000168439
Change order for $85,893 covering support structures, concrete encasement, routing, and patching for fuel oil lines and enclosures at 7 World Trade Center.
Similar indexed content
NYC-WTC_000172028
Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
Similar indexed content