2. Support utilities to remain in place.
3. For utilities to be relocated, arrange for such relocation with
appropriate utility companies.
4. Remove all inactive, abandoned utilities within the limits of the area
to be excavated, whether or not such utilities are indicated for removal
on the Drawings.
1. Permanently close open ends of abandoned underground utilities which
are indicated to remain, with sufficiently strong closures to
withstand pressures which may result after closing.
2; Use suitable methods and materials to effect such closures, as
I required and as approved by the Engineer.
B. Unknown Utilities:
I 1. When utility lines, that are not made known or indicated rare
K 1 encountered within the area of operations, notify the Engineer in ample
time for the necessary measures to be taken. . . ;
I 2. Do not disrupt any service until required action on such lines has been
determined by the Engineer.
3.05 PUMPING AND DRAINAGE
A. At all times during construction of the work and at its completion for final
inspection, by the Engineer, provide and maintain ample means and suitable
equipment, consistent with conditions encountered, to promptly remove and
properly dispose of all water entering excavations or other parts’ of the
B. Control surface and subsurface water infexcavations at all"times until the
structures to be built therein are completed and backfilled to approximately
final grades.
C. Dispose of water in a suitable manner and as shown on the Drawings So as to
avoid damage to adjacent property, existing structures and all work' under
construction. Do not pump drainage water on to the streets without the
written permission in advance from the Engineer.
D. Provide and maintain settling basins and sumps for catching and holding
settleable matter. These shall be frequently cleaned and maintained.
Wherever water containing mud, clay, sand or other material/in suspension,
is pumped from excavations, make suitable provisions to insure that the flow
will be unobstructed. Take precautions to avoid pumping water through
freshly placed concrete.
E. At no time shall the uplift pressure on any structure exceed 80 percent of
the downward pressure produced by the weight of the structure and any
backfill in place. The Contractor shall submit his proposed methods of
controlling uplift pressure to the Engineer for approval prior to the start
of excavation.
Contract 02220-4 Excavation and
1-02-21064-0-0 Backfilling