2. Air monitoring technicians must be on-site during clean-up activities to collect final clearance
samples.
3. The Project Monitor shall ensure that the clean up activities comply with the NYCDEP Scope of
Work.
Post Clean-up Air Sampling Procedure must be as followed:
a) Sampling shall not begin until a visual inspection confirms the absence of
visible debris.
b) All surfaces must be completely dry prior to the start of sampling.
c) Sampling equipment shall be placed at representative locations within the
work area and away from obstructions. The sampling cassette must be
placed on a tripod and not taped to existing surfaces.
d) Air conditioning units where applicable shall be run/operated at least 15
minutes prior to the start of sampling. The air conditioning units shall operate
continuously throughout the sampling. HVAC systems shall be in operation
during sampling.
e) Forced air equipment (e.g. leaf blowers) may be used only after written
authorization by the occupant or his/her authorized representative. The
project manager shall advise the occupant or his/her authorized representative
on the advantages and disadvantages regarding the use of the equipment and
obtain the individual’s signature authorizing use. Before the start of sampling,
forced air equipment (such as a 1 horsepower leaf blower) may be used to
direct exhaust air against walls, ceilings, floor, ledges and other surfaces.
When directing the exhaust, caution shall be taken to minimize disturbance
and potential damage to fiimishings and personal belongings.
f) One 20-inch fan shall be installed per 10,000 cubic feet of room space and run
at low speed. The fan shall operate continuously throughout sampling and
shall not be turned off until sampling is completed.
g) For studio apartments 3 samples shall be collected. For 1-bedroom
apartments and above 5 samples shall be collected. Technicians shall collect a
volume of 3000 liters per sample using a flow rate of 10 liters per minute.
h) Samples must be labeled and accompanied with completed chain of custody
forms before shipping to the designated laboratory.
i) Project Monitor shall perform all final visual inspections.
j) All information must be maintained on a data based software program that is
acceptable to the USEPA.
4. Project reports, including a project completion sign-off signed by the project monitor and the occupant
or his/her authorized representative, must be typed and forwarded to USEPA with a copy to
NYCDEP.