2/19/03
/
Proposal to Expedite Clean-up of Indoor Residential Units/Common Spaces
Facts:
• HVAC evaluation process taking much longer than anticipated - issues with
access agreements and mechanical drawings
• Common spaces show no evidence of residential WTC dust
• HVACs to be tented in public spaces eliminating the possibility of cross
contamination
• Exhausts to be tented in areas of brush penetration; all other open vents to be
sealed during thecleaning process
• Currently at 400 apartments per week, it will take 8 to 9 weeks to complete the
project. Stock of apartments available for cleanup does not come close right now,
to reach 400 per day, thus will take longer than 9 weeks to complete.
• Release all apartments and common spaces for cleaning, while HVAC evaluations
are being conducted
Justification:
• Since routes of possible contamination will be sealed, the possibility of cross
contamination to a common space/residential unit already cleaned is eliminated.
• This will allow the stock of apartments/common spaces to reach its maximum
quickly, thus ensuring the contractors the maximum number of apartments to call,
schedule and clean as per the contract.
• This will effectively reduce the present time span of the project, despite our many
efforts to shorten the process.
Precedent
• The building at 222 Rector Street has had all the apartments cleaned, however,
recently the owner has changed his mind regarding cleaning HVAC/exhausts and
EPA has agreed to an HVAC/exhaust cleanup. In effect, this building will be
cleaned using the same methods and procedures noted above.