Cleaning to be done in 11 Weeks
(Mid April)
1. Implementation of cancellation policy
a. Meeting with monitoring contractor/quad leader by 2/3/03
b. Clearly explain policy to all contractors by 2/3/03
c. Assist monitoring contractors in developing spreadsheet of all calls for tracking purposes
d. All residents to be called by 2/15/03
e. Initial call - send letter right away
f. Simultaneous letter/3 additional calls within same 2-week period
g. No response within two-week period/official cancellation
2. Total number of common spaces and apartments need to be delineated (within building
requests)
3. All HVAC/Exhaust inspections must be done by February 22"*^ (3 weeks)
Refer to attached chart
4. Group all buildings by street address/proximity
5. Apartments/common spaces multiple
Refer to attached chart
6. Reinforce policy that residents cannot change from test only to test and clean
7. License/Access Agreement Policy
8. Send cover memo to building owner with timeframe when access agreement if due (2
weeks)
9. Need to get access agreements quickly (within 1 week) in order to continue inspections.