1. Implementation of cancellation policy
a. Meeting with monitoring contractor/quad leader by 2/3/03
b. Clearly explain policy to all contractors by 2/3/03*
c. Assist monitoring contractors in developing spreadsheet of all calls for trackmg purposes 4?
d. All residents to be called by 2/15/03
e. Initial call - send letter right away
f. Simultaneous letter/3 additional calls within same 2-week period
g. No response within two-week period/official cancellation
2. Total number of common spaces and apartments need to be delineated (within building
requests) L—.
3. All HVAC/Exhaust inspections must be done by February 22"'' (3 weeks)
Refer to attached chart
4. Group all buildings by street address/proximity
5.''^Apartments/common spaces multiple
Refer to attached chart
6. Reinforce policy that residents cannot change from test only to test and clean
License/Access Agreement Policy
Send cover memo to building owner with timeframe when access agreement if due (2
weeks)
X. Need to get access agreements quickly (within 1 week) in order to continue inspections.
f
Uta
NYC-WTC_000140762
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000140762Source: NYC Law Department, mirrored locally
Request to the Department of Transportation for a fee waiver regarding sidewalk closures needed for exterior debris cleaning operations near the WTC site.
A project proposal outlining the timeline, methods, and justification for cleaning HVAC systems in residential units affected by World Trade Center dust.
A project proposal outlining the timeline, methods, and justification for cleaning HVAC systems in residential units affected by World Trade Center dust.
A project proposal outlining the timeline, methods, and justification for cleaning HVAC systems in residential units affected by World Trade Center dust.
Introduction to a cross-agency group tasked with identifying contaminants of concern and establishing health-based screening levels for the indoor environment.