Cleaning to be done in 11 Weeks
(Mid April)
1. Implementation of cancellation policy
a. Meeting with monitoring contractor/quad leader by 2/3/03
b. Clearly explain policy to all contractors by 2/3/03
c. Assist monitoring contractors in developing spreadsheet of all calls for tracking purposes
d. All residents to be called by 2/15/03
e. Initial call - send letter right away
f. Simultaneous letter/3 additional calls within same 2-week period
g. No response within two-week period/official cancellation
2. Total number of common spaces and apartments need to be delineated (within building
requests)
3. All HVAC/Exhaust inspections must be done by February 22"^^ (3 weeks)
Quad A 15 inspections/week
Quad B 9 inspections/week
Quad C 15 inspections/week
Quad D 6 inspections/week
4. Group all buildings by street address/proximity
5. Quad A 1143 104 per week
20 apartments and/or common spaces/day
Test Only 235 4/day
Quad B 1356 61 per week
12 apartments and/or common spaces/day
Test Only 230 4/day
Quad C 1056 98 per week 20 per day
Test Only 213 19 per week 4 per day
Quad D 1015 92 per week 18 per day
Test Only 122 20 per week 4 per day
6. Reinforce policy that residents cannot change from test only to test and clean
7. License/Access Agreement Policy
8. Send cover memo to building owner with timeframe when access agreement if due (2
weeks)