HVAC consulting services invoice, NYC WTC site, 2003

Machine-extracted title · confidence 95%

Invoice for HVAC consulting services provided at the World Trade Center site in 2003.

NYC-WTC_000135339–000135553
Page image
Scanned page image, NYC-WTC_000135552
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

WTC HVAC Consulting Quad C Summary of Visits Date IBuilding I Comments Roof top clean up completed. TX-1 and TX-8 risers cleaned. 3/25/03 49 Fulton St. Apartments connected to risers sealed off. Continued cleaning of the lower section of the risers. Gained 3/26/03 49 Fulton St. access to apartments, set up tents and cleaned according to rocedure. Started and completed cleaning. Inspected by Tony Gallo from 3/28/03 75-81 Nassau Dust Dusters and was confirmed that scope was met. Completed cleaning the 8 roof exhaust fans and risers. Finishing 3131/03 275 Water St. vents and rest of building on 4/1. 4/2/03 66 Frankfort St. Completed cleaning of compactor exhaust fan. 4/2/03 80 Beekman St. Completed cleaning of elevator shaft exhaust fan. Cleaning rescheduled for Mayl or 2 due to Passover and possible 4/7/03 90 Beekman St. strike. Cleaning rescheduled for Mayl or 2 due to Passover and possible 4/7/03 90 Gold St. strike. Started cleaning of exhaust fans and risers. Used Tement Technologies HEPA Aire 2500 Portable VAC, with Champell 4/14/03 33 Gold St. Hansfield W261001AJ Compressor (8.lscfm 0 40 psi, 6.1 scfm 0 90 psi, 125 psi max). Continued and completed cleaning of exhaust fans and risers. 4/15/03 33 Gold St. Started cleaning of apartments in 2 riser lines and then the rest of the affected building on the 7th floor. Continued and completed cleaning of apartments' entire building completed. Witnessed re-inspection. 2 exhausts fans failed re- 4/16/03 33 Gold St. inspection since they were inaccessible to clean with standard equipment (vacuum or by hand). They wilt be re-cleaned via power washer at a later date. Gained access to all apartments and sealed off the vents. There are two apartments that share an impacted riser that are part of the 4/28/03 176 Broadway 11 Maiden Lane apartment complex, totaling 2 bathrooms and 1 kitchen. Scheduled to start exhaust fan cleaning tomorrow and individual apartments on the following day until thurs. Completed cleaning 6 exhaust fans and 3 risers. The day was cut 4/29/03 176 Broadway short due to rain. Completed cleaning of all exhaust fans and risers. Identified one exhaust fan and riser as part of the adjacent building (11 Maiden 4/30/03 176 Broadway Ln.) which is not in the scope of work and therefore has been removed. Started and completed cleaning of AC unit. Started cleaning of apartments and finished cleaning 3 apartments of the 7th floor 5/1/03 176 Broadway through the penthouse floor. Entire building scheduled for completion on 5/2. 5/1/03 176 Broadway Completed apartment cleaning. Entire building cleaning completed Power washed the remaining 2 exhaust fans that had failed 5/1/03 33 Gold St. inspection

NYC-WTC 000135552

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000135552Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →