Summary of Visits
Date IBuilding Comments
Continued cleaning on schedule. Total of 6 exhaust fans and
4/2/03 275 Greenwich St. risers have been completed. No one was present to field verify
the quantities of cleaned equipment.
Started cleaning of HV unit and associated ductwork in
4/8/03 295 Greenwich St. basement. Correctly used 2 HEPA vacuum units in series for
exhausted (cleaned) air. Should complete building by 4/9.
Started and completed cleaning of exhaust riser. Cleaning of
4/9/03 295 Greenwich St.
entire building completed.
Started and completed cleaning of exhaust riser. cleaning of
4/10/03 130 Water St. entire building completed. Anthony Faloduro of Cole Consulting
was present for the duration of the cleaning.