Part TV- Waste Management Plan
133-1 ' n' wiehStreer21-23 Thames Street
Airtek Project 05-0701 —August 10, 2005
concern that they might be hazardous waste due to the inherent
composition of the component, subcomponent or waste stream (e.g., light
ballasts which may contain PCBs, items coated with lead-based paint).
Non-Porous Deconstruction Waste may be managed by either of two
options. The Abatement Subcontractor may choose to clean the non-
porous surfaces in accordance with procedures outlined in the Asbestos
and COPC Abatement Plan of the Work Plan. The resulting cleaned
material will not be sampled unless it is painted; in that instance, sampling
will be performed as described in Section 7.0 of this Plan. Alternatively,
based on field conditions and decisions regarding the use of its labor force,
the Abatement Subcontractor may choose to not clean the surfaces and
instead manage those uncleaned non-porous materials as asbestos waste at
a minimum or otherwise, if required, as determined by the RCRA
characteristics sampling.
4.3 Miscellaneous Materials
Due to the small scale, simple use, and relative antiquity of the buildings
and their systems, additional miscellaneous regulated and/or hazardous
waste is anticipated to be very limited in nature and scope. The
Environmental Consultant will conduct daily inspections of the abatement
work area to identify suspect components for segregation and testing
and/or other determination.
Any material classified as "unknown" during the project will require
sample collection and analysis for full RCRA characteristics in accordance
with 40 CFR Part 261 (as described in Section 4.1.3 of this Plan) and will
be disposed of based upon the results of that sampling and the nature of
the waste. If the material is classified as RCRA hazardous waste,
additional sampling may be required for "total" concentrations of specific
contaminants to determine whether the waste may be land filled or is "land
banned"; the contaminants to be analyzed for will depend on the specific
waste classification of the waste.
4.4 Structure and Facade
Dust sampling for hazardous waste characteristics has been performed in
advance of sampling of materials impacted by dust. It is anticipated that
the dust classification sampling will indicate that the dust is not a
characteristic hazardous waste, and then by extension, any non-hazardous
materials potentially impacted by dust (i.e., the Structure & Facade of the
building would also not be hazardous. Random confirmatory sampling of
the various deconstruction waste categories will be conducted to confirm
the status of the structure and facade as C&D waste.
7
NYC-WTC 000135130