Part IV- Waste Management Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701— Rev 1, September 16, 2005
The resulting cleaned material will not be sampled unless it is painted; in
that instance, sampling will be performed as described in Section 7.0 of
this Plan. Alternatively, based on field conditions and decisions regarding
the use of its labor force, the Abatement Subcontractor may choose to not
clean the surfaces and instead manage those uncleaned non-porous
materials as asbestos waste at a minimum or otherwise, if required, as
determined by the RCRA characteristics sampling.
4.3 Miscellaneous Materials
Due to the small scale and simple use (commercial/residential) of the
buildings and their systems, additional miscellaneous regulated and/or
hazardous waste is anticipated to be very limited in nature and scope. The
Environmental Consultant will conduct daily inspections of the abatement
work area to identify suspect components for segregation and testing
and/or other determination.
Any material classified as "unknown" during the project will require
sample collection and analysis for full RCRA characteristics in accordance
with 40 CFR Part 261 (as described in Section 4.1.3 of this Plan) and will
be disposed of based upon the results of that sampling and the nature of
the waste. If the material is classified as RCRA hazardous waste,
additional sampling may be required for "total" concentrations of specific
contaminants to determine whether the waste may be land filled or is
restricted from land disposal pursuant to 40 C.F.R. Part 268; the
contaminants to be analyzed for will depend on the specific waste
classification of the waste.
4.4 Structure and Facade
Dust sampling for hazardous waste characteristics has been performed in
advance of sampling of materials impacted by dust. It is anticipated that
the dust classification sampling will indicate that the dust is not a
characteristic hazardous waste, and then by extension, any non-hazardous
materials potentially impacted by dust (i.e., the Structure & Facade of the
building would also not be hazardous. Due to the limited nature of the
preliminary sampling, confirmatory sampling of the various
deconstruction waste categories will be conducted to confirm the status of
the structure and facade prior to commencement of the demolition phase.
For materials requiring sampling, a representative sampling strategy will be used
as detailed in section 6.0, and composite samples representative of the final waste
streams will be collected. The locations and frequency of samples to be combined
into composite samples shall be determined by the Environmental Consultant
such that a representative sample of the waste type has been obtained. All
sampling personnel shall be familiar with sample collection and waste storage
protocols and shall have undergone Hazard Communication training in
7
NYC-WTC 000134321