EPA work plan review, 133-135 and 21-23 buildings, August 2005
Machine-extracted title · confidence 75%
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.
Part III — Health & Safety Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701— Rev 1, August 11, 2005
A licensed abatement contractor must perform the removal of all friable and non-friable ACM.
Airtek believes that the implementation of these recommendations will serve to best protect
human health and the environment.
To assure that the removal of the aforementioned ACM is properly and effectively carried out,
the following recommendations are proposed by Airtek:
D. Develop and implement a schedule that outlines the time frame for removal of ACM.
E. Develop complete and concise specifications to effectively deal with removal of the ACM.
These specifications should be developed to comply with all applicable Federal, State and
Local regulations.
F. Retain the service of an independent testing laboratory to monitor the air for possible
asbestos contamination before, during and after the removal work. Retain all
documentation and correspondence from the removal contractor, the testing laboratory and
related items in a permanent record.
5.0 ASBESTOS QUANTITY SCHEDULE:
Approximate asbestos quantity schedules are presented on the following table:
TABLE I
SUMMARY OF INSPECTION RESULTS FOR ASBESTOS
21-23 THAMES STREET
PROPOSED SUSPECT ACM THAT LAB APPROXIMATE
WORK MAY BE AFFECTED ACM NOTES/SPECIFIC LOCATION
RESULT
QUANTITY
Flashing ACM 100 SF 5th Floor Roof
Bulkhead Tar ACM 75 SF 5th Floor Roof
Roofing Material ACM 350 SF 5th Floor Roof
Flashing ACM 41 SF 1 Floor Roof
Roofing Material ACM 105 SF 1 5t Floor Roof
Brick Mortar ND 0 SF Entire
Coping Stone Mortar ND 0 SF 5th Floor Roof
Coping Stone Caulk ACM 1 SF 5th Floor Roof —15 LF total
Window Caulk ACM 9 SF Masonry Openings - 210 LF total
Window Glazing ND 0 LF Entire
Wall Plaster (White &
ND 0 SF Entire
Brown Coats
2" Floor, Storefront between Indian Rest.
& Eat & Run, Basement, Apartments —
Aircell Pipe Insulation ACM 50 LF This is the amount that was visible to the
investigator. Pipe Insulation is assumed to
exist behind/in the wall cavities/chases.
Ceiling Plaster (White &
Brown Coats ND 0 SF Entire
Sheetrock & Joint ND
Compound 0 SF Entire
Rubber Tile Mastic ND 0 SF Between Indian Restaurant and Eat & Run
Cementitious Duct
ND 0 SF Eat & Run
Insulation
White Block Pipe
ACM 8 LF Eat & Run
Insulation
Tile Grout ND 0 SF Eat & Run
Total Approximate Quantity of ACM 681 SF & 58 LF
NYC-WTC 000135078
OCR can misread numbers and units. Confirm readings against the page image before using them.