Change order #92 submission, 7 World Trade Center, Aug 1999 — page 1

WTC 7 / 7DCAS / Mayor's Office of Emergency Management ®7 World Trade Center ®Change Order #092 ®Arnb. Job #S57-5175
NYC-WTC_000168396Machine-extracted title
Memo or letter

Summary Letter submitting change order #92 to install a kindoff on a wall in the press room for $380.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #91 submission, 7 WTC, Aug 1999 — page 1

WTC 7 / 7DCAS / 7 World Trade Center Mayor's Office of Emergency Management-1st, 7th, & 23rd Flrs Change Order #91
NYC-WTC_000168397Machine-extracted title
Memo or letter

Summary Letter submitting change order #91 for $6,565 to remedy water leakage on the 7th floor of 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #91 submission, 7 WTC, Aug 1999 — page 2

WTC 7 / 7DCAS / 7 World Trade Center Mayor's Office of Emergency Management-1st, 7th, & 23rd Flrs Change Order #91
NYC-WTC_000168398Machine-extracted title
Memo or letter

Summary Letter submitting change order #91 for $6,565 to remedy water leakage on the 7th floor of 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #91 submission, 7 WTC, July 1999 — page 1

WTC 7 / 7DCAS / Mayor's Office of Emergency Management 7 World Trade Center Change Order #091 Amb. Job #S57-5175
NYC-WTC_000168399Machine-extracted title
Memo or letter

Summary Letter from Ambassador Construction submitting change order #91 for $6,565 to remedy leakage on the 7th floor of 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #91 submission, 7 WTC, July 1999 — page 2

WTC 7 / 7DCAS / Mayor's Office of Emergency Management 7 World Trade Center Change Order #091 Amb. Job #S57-5175
NYC-WTC_000168400Machine-extracted title
Memo or letter

Summary Letter from Ambassador Construction submitting change order #91 for $6,565 to remedy leakage on the 7th floor of 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Job memorandum regarding water system, 7 WTC, Aug 1999 — page 1

WTC 7 / 7DCAS / O.E.M. @ T.W.T.C.
NYC-WTC_000168401Machine-extracted title
Memo or letter

Summary Internal job memorandum proposing an automatic pump and collection tank unit to resolve limited flow in the 7th floor domestic water booster system.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #89 submission, 7 WTC, June 1999 — page 1

WTC 7 / 7DCAS / 7 World Trade Center Mayor's Office of Emergency Management-1st, 7th, & 23rd Flrs Change Order #89
NYC-WTC_000168402Machine-extracted title
Memo or letter

Summary Letter submitting change order #89 for $7,553 to install power and control wiring for the Inergen system in the fuel oil tank room.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #89 submission, 7 World Trade Center, June 1999 — page 1

WTC 7 / 7DCAS / Mayor's Office of Emergency Management 7 World Trade Center Change Order #089 Arnb. Job #S57-5175
NYC-WTC_000168403Machine-extracted title
Memo or letter

Summary Letter submitting change order #89 for power and control wiring for the Inergen system in the fuel oil tank room.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #89 submission, 7 World Trade Center, June 1999 — page 2

WTC 7 / 7DCAS / Mayor's Office of Emergency Management 7 World Trade Center Change Order #089 Arnb. Job #S57-5175
NYC-WTC_000168404Machine-extracted title
Memo or letter

Summary Letter submitting change order #89 for power and control wiring for the Inergen system in the fuel oil tank room.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #88 approval, fuel oil line, 7 WTC, June — page 1

WTC 7 / 7DCAS / Change Order #88 Mayor's Office of Emergency Management 7 World Trade Center New York, New York
NYC-WTC_000168405Machine-extracted title
Memo or letter

Summary Memo from Citywide Administrative Services approving a reduced cost of $130,000 for the supply and installation of a new fuel oil line.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #88 approval, fuel oil line, 7 WTC, June — page 2

WTC 7 / 7DCAS / Change Order #88 Mayor's Office of Emergency Management 7 World Trade Center New York, New York
NYC-WTC_000168406Machine-extracted title
Memo or letter

Summary Memo from Citywide Administrative Services approving a reduced cost of $130,000 for the supply and installation of a new fuel oil line.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change Order #88 submission, 7 WTC, June 1999 — page 1

WTC 7 / 7DCAS / Mayor's Office of Emergency Management 7 World Trade Center Change Order #088 Amb. Job #S57-5175
NYC-WTC_000168409Machine-extracted title
Memo or letter

Summary Contractor submits Change Order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at the Mayor's Office of Emergency Management.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change Order #88 submission, 7 WTC, June 1999 — page 2

WTC 7 / 7DCAS / Mayor's Office of Emergency Management 7 World Trade Center Change Order #088 Amb. Job #S57-5175
NYC-WTC_000168410Machine-extracted title
Memo or letter

Summary Contractor submits Change Order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at the Mayor's Office of Emergency Management.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change order #87 submission, 7 WTC, June 1999 — page 1

WTC 7 / 7DCAS / 7 World Trade Center Mayor's Office of Emergency Management-1st, 7th, & 23rd Flrs Change Order #87
NYC-WTC_000168411Machine-extracted title
Memo or letter

Summary Letter submitting change order #87 for $1,276 to install a UPS conversion kit in an office at the Mayor's Office of Emergency Management.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Change Order #87 submission, 7 WTC, June 1999 — page 1

WTC 7 / 7DCAS / Mayor's Office of Emergency Management®7 World Trade Center®Change Order #087®Amb. Job #S57-5175
NYC-WTC_000168412Machine-extracted title
Memo or letter

Summary Contractor submits Change Order #87 for $1,276 to install a UPS conversion kit in an office at the Mayor's Office of Emergency Management.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Contractor application for payment, 7 WTC, May 1999 — page 1

WTC 7 / 7DCAS / Contractor's Application for Payment
NYC-WTC_000168414Machine-extracted title
Unclassified

Summary Partially legible contractor application for payment document associated with construction work at 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Contractor application for payment, 7 WTC, May 1999 — page 2

WTC 7 / 7DCAS / Contractor's Application for Payment
NYC-WTC_000168415Machine-extracted title
Unclassified

Summary Partially legible contractor application for payment document associated with construction work at 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Contractor application for payment, 7 WTC, May 1999 — page 3

WTC 7 / 7DCAS / Contractor's Application for Payment
NYC-WTC_000168416Machine-extracted title
Unclassified

Summary Partially legible contractor application for payment document associated with construction work at 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Contractor application for payment, 7 WTC, May 1999 — page 4

WTC 7 / 7DCAS / Contractor's Application for Payment
NYC-WTC_000168417Machine-extracted title
Unclassified

Summary Partially legible contractor application for payment document associated with construction work at 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Contractor application for payment, 7 WTC, May 1999 — page 5

WTC 7 / 7DCAS / Contractor's Application for Payment
NYC-WTC_000168418Machine-extracted title
Unclassified

Summary Partially legible contractor application for payment document associated with construction work at 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of