AMBASSADOR CONSTRUCTION CO,. INC.
R JUL 2 6 1999
July 22, 1999
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York, NY 10048
Re; Mayor’s Office of Emergency Management
7 World Trade Center
Change Order #091
Amb. Job #S57-5175
Dear Mr. Weems;
We are pleased to submit herewith our change order #091 to perform the following
work at the above referenced premises for the sum of SIX THOUSAND FIVE
HUNDRED SIXTY FIVE DOLl_ARS ($6,565.00);
As per Cosentini’s memo to Swanke Hayden Connell regarding the 7th floor
Domestic Booster System bearing drips, the following are the costs associated to
remedy the leakage;
Furnish and install federal pump unit
Furnish and install 2" funnel drain
Connect pump discharge to existing discharge $3,775.00
Furnish and install one (1) separate circuit for pump $1,875.00
Subtotal $5,650.00
General Conditions 452.00
Overhead & Fee 366.00
Insurance ,97.00
Total $6,565.00
EXCLUSIONS
- Work on overtime
- Vent for pump
Continued. . .