Change Order #91 Memo, MOEM 7th Floor, August 1999

Machine-extracted title · confidence 95%

Memo submitting Change Order #91 for $6,565 to remedy water leakage on the 7th floor of 7 World Trade Center associated with the Mayor's Office of Emergency Management.

NYC-WTC_000172576–000172577

Folder label: “7 World Trade Center Mayor's Office of Emergency Management-1st, 7th, & 23rd Flrs Change Order #91

Page image
Scanned page image, NYC-WTC_000172576
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Silverstein Properties, Inc. 1 St S y 7 World Trade Center New York, N.Y. 10048 Telephone; 212-619-6569 iqtci M36 -M P S'- Fax; 212-732-5190

August 2, 1999

Mr. Glenn Pymento Department of City Wide Administrative Services Division of Real Estate Services 1 Centre Street, DRES - Room 2000 North New York, New York 10007

RE: 7 World Trade Center Mayor's Office of Emergency Management-1^ 7^, & 23"* Firs Change Order #91 Dear Mr. Pymento:

Attached please find change order #91 in the amount of $6,565.00 submitted by Ambassador Construction for the following scope of work:

As per Cosentini's memo to Swanke Hayden Connell regarding the 7*^ floor Domestic Booster System bearing drips, the following are the costs associated to remedy the leakage:

Furnish and install federal pump unit Furnish and install 2" funnel drain Connect pump discharge to existing discharge Above items $3,775.00

Furnish and install one separate circuit for $1,874.00 pump

Subtotal $5,650.00 General Conditions $452.00 Overhead and Fee $366.00 Insurance $97.00 $6,565.00 Exclusions: Work on overtime Vent for pump

NYC-WTC_000172576

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000172576Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171689 · Box 7DCAS

Administrative memo submitting change order costs for pump installation and circuit work at 7 World Trade Center dated August 2, 1999.

Similar indexed content

NYC-WTC_000168446 · Box 7DCAS

Contractor submits Change Order #78 for $6,629 to reinstall speakers and fire devices during ceiling tile work.

Similar indexed content

NYC-WTC_000168437 · Box 7DCAS

Contractor submits Change Order #44R for $85,893 to install fuel lines and supports at 7 World Trade Center.

Similar indexed content

Compare copies and versions →