July 7, 1999
Ms. Catherine T. Giliberti
Silverstein properties, Inc.
7 World Trade Center
New York, NY 10048
Re: Change Order # 88
Mayor’s Office of Emergency Management
7 World Trade Center
New York, New York
Dear Ms. Giliberti:
We write with reference to CO #88 submitted by Ambassador Construction Co on 6/10/1999 in
the amount of $135,957.00 for the supply and installation of the fuel oil line as per the new route.
The change order has been reviewed and the cost has been negotiated down to $130,000.00:
In view of the foregoing, an amount of $130,000.00 is hereby approved, subject to audit, for the
fuel oil line.
An amount of $85,000.00 already approved by this office for the fuel oil line as per the old
design has been voided by this letter. Therefore, a credit amount of $85,000.00 is also approved
by this letter.
The following is a breakdown of the project’s budget.
Construction cost budget $14,287,986.00
Construction cost Budget (Revised) $14,287,986.00
Less Landlord’s Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,619,128.00
Construction cost approved on 6/2/98 $12,864,619.00
NYC-WTC_000168405