NYC Law Department release
Independent mirror · updated as the City releases more · v1.2.6
← Document results/7DCAS/Change Order #88 Mayor's Office of Emergency Management 7 World Trade Center New York, New York
Document / 2 pages

Change order #88 approval, fuel oil line, 7 WTC, June

Machine-extracted title · confidence 95%

Memo from Citywide Administrative Services approving a reduced cost of $130,000 for the supply and installation of a new fuel oil line.

NYC-WTC_000168405–000168406

Folder label: “Change Order #88 Mayor's Office of Emergency Management 7 World Trade Center New York, New York

Page image
Scanned page image, NYC-WTC_000168406
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

-2-

Amount approved by CO on 7/8/98 $ 117,684.00 Amount approve by CO on 8/11/98 $ 7,000.00 Amount approved by CO on 9/14/98 $ 102,705.00 Amount approved by CO on 9/21/98 $ 28,442.00 Amount approved by CO on 10/22/98 $ 26,483.00 Amount approved by CO on 10/30/98 $ 42,887.00 Amount approved by CO on 12/1/98 $ 125,453.00 Amount approved by CO on 12/29/98 $ 27,821.00 Amount approved by CO on 1/4/99 $ 3,941.00 Amount approved by CO on 1/25/99 $ 78,288.00 Amount approved by CO on 2/10/99 $ 22,721.00 Amount approved by CO on 3/11/99 $ 220,262.00 Amount approved by CO on 3/25/99 $ 4,874.00 Amount approved by CO on 4/8/99 $ 85,000.00 Amount approved for fuel oil line $ 130,000.00 Credit amount approved for previously approved fuel line 85,000.00) Total construction cost approved $13,803,180.00 Less Landlord contribution $ 1,668,858.00 Amount chargeable to the City $12,134,322.00 Balance remaining in Budget $ 484,806.00

If you have any question, please call Glenn Pymento at (212) 669-8094. Thank you for your cooperation.

Sincerely,

/fA Executive Director of Space Design/DRES

cc: G. Pymento, DRES^ M. Mathew, V. Castagnola, DRES J. Menasce, DRES J. Domingvez, DRES W. Weems, Silverstein Properties, Inc.

c:/Mathew/giliberti 13.doc/kc

NYC-WTC_000168406

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000168406Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Approval letter for Change Order #104, Nov 1999 · Box 7DCAS

NYC-WTC_000171623

Letter from DCAS approving a negotiated cost of $50,000 for conduit and fiber optic installation at the Mayor's Office of Emergency Management.

2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.991

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171737 · Box 7DCAS

Memo approving a negotiated cost of $130,000 for fuel oil line supply and installation at the Mayor's Office of Emergency Management.

Filed in the same folder

NYC-WTC_000171694 · Box 7DCAS

Memo approving a negotiated cost of $130,000 for fuel oil line supply and installation at 7 World Trade Center dated July 7, 1999.

Similar indexed content

NYC-WTC_000171623 · Box 7DCAS

Letter from DCAS approving a negotiated cost of $50,000 for conduit and fiber optic installation at the Mayor's Office of Emergency Management.

Similar indexed content

Compare copies and versions →