SECTION 02082
a) Work shall occur as scheduled.
b) Horizontal surfaces near the blanking operations shall be protected with 6-mil
polyethylene sheeting.
c) Plastic drapes shall be used to enclose the immediate area.
d) Contractor to position and operate air filtration devices and HEPA-vacuums in the
area to clean space after blanking operations.
e) All personnel involved with this work shall receive personal protection (i.e.
respirators and disposable suits).
F. Upon loss of negative pressure or electric power, all work activities in an area shall cease
immediately and shall not resume until negative pressure and/or electric power has been fully
restored. When a power failure or loss of negative pressure lasts, or is expected to last, longer
than thirty (30) minutes, the following sequence of events shall occur.
1. All make up air inlets shall be sealed airtight.
2. All decontamination facilities shall be sealed airtight after evacuation of all personnel
from the Work Area.
3. All adjacent areas shall be monitored for potential fiber release upon discovery of and
subsequently throughout, power failure.
3.07 LOCKOUT OF HVAC SYSTEMS AND ELECTRIC POWER
A. Prior to the start of any prep work, the Contractor shall employ skilled tradesmen with limited
asbestos licenses for the following work:
1. Disable all ventilating systems or other systems bringing air into, or exhausting air out of,
the Work Area. Disable system by disconnecting wires removing circuit breakers, by
lockable switch or other positive means to ensure against accidental re-starting of
equipment.
2. Lockout power to the Work Area by switching off all breakers and removing them from
panels or by switching and locking entire panel. Label panel with following notation:
“DANGER CIRCUIT BEING WORKED ON”. Give all keys to Facility.
3. Lock out power to circuits running through Work Area whenever possible by switching
off and removing breakers from panel. If circuits must remain live, the Facility shall
notify Contractor in order that he may secure a variance from NYCDEP. Protect all
conduit and wires to remain and label all active circuits at intervals not to exceed 3 feet
with tags having the following notation: “DANGER LIVE ELECTROCUTION
HAZARD”. Label all circuits in all locations including hidden locations that may be
affected by the work in a similar manner.
02082-68
CITY_21 MCI 00_014563841
NYC-WTC_000454641