Scope of Work B
Application; Avisual inspection was performed and thepresenceofaccumulations ofdebris (including large
or significant amounts of dust) from the collapse of the WTC was identified by EPA or designee.
In some unique circumstances, Scope B may be applied on a limited basis within a unit as determined
necessary by the Monitoring Contractor in consultation with EPA. Residents may be present depending on
these unit specific circumstances. In cases where clean up areas can be isolated by closing doors or by the
erection ofcontainment barriers, the resident may be present in the unit. In all other applications of Scope
B it is assumed that residents will not be present.
1. A site specific work plan will be prepared for review and approval by EPA prior tp the start ofwork.
This work plan will include detailed procedures for the renioval ofdust and debris and the cleaning.
2. An ACP-7 form asbestos project notification form shall be submitted, as required by Title 15,
Chapter 1 oftheRCNY, directly to the NYCDEP Asbestos Control Program prior to the start of
work. NYS DOL notification shall be submitted.
3. At least one asbestos supervisor shall bepresent at each work place (workplace is defined in Title
75, Chapter 1 RCNY as the work area and the decontamination enclosure system).
4. Personal protective equipment including disposable clothing, gloves, and respirators shall be worn
during this clean-up activity in accordance with OSHA rules and regulations.
5. Warning signs shall W^dSt^ at the approach to the work area.
6. A worker decontamination enclosure system shall be installed at the entrance to the work area. A
remote decontamination enclosure system shall be considered when appropriate i.e. inability to
comply with the provision due to space limitation or other agency rules, such as for compliance with
NYCFD egress requirements.
7. HVAC systems shall be shut down and locked out or isolated locally. The site specific work plan
shall provide additional information on the HVAC system and proposed procedures for shutdown
or isolation.
8. Isolation barriers shall be installed with two layers of6-mil polyethylene sheeting and sealed with
tape.
9. Negative pressure ventilation equipment shall be installed and operated during all clean-up activities.
Equipment shall run continuously until clearance air monitoring. A minimum ofone air change every
30 minutes shall be provided. When ducting to the outside is not possible, a second negative pressure
ventilation unit compatible with the primary unit capacity may be connected in series.