Exterior sealant/caulking abatement specs, P.S. 92M

Machine-extracted title · confidence 53%

Specifications for asbestos-containing exterior sealants and caulking materials abatement.

NYC-WTC_000454574–000454656
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

SECTION 02082 work.

It is the Contractor’s sole responsibility to plan and perform the work in such a manner that it is brought to successful completion. This includes Work Area preparation, removals and final cleaning to an acceptable standard.

B. The Abatement Contractor shall also develop a detailed plan of action to respond to the release of airborne asbestos fibers in the event of an emergency. This plan (which must be accepted by the Construction Manager, Resident Engineer and School Principal) is to include but not limited to; procedures to isolate and eliminate ACM, emergency evacuation procedures, telephone numbers of all relevant parties, air monitor, etc.

C. Prior to start of preparatory work as discussed, the Contractor shall attend a preconstiuction conference and walk-through attended by Construction Manager and Testing Lab Environmental Control Representative (ECR).

Agenda for this conference will include but not necessarily be limited to:

1. Contractor’s scope of work, work plan and schedule

2. Contractor’s safety and health precautions including protective clothing and equipment and decontamination procedures.

3. Testing laboratory’s air monitoring plan.

4. Contractor’s work procedures including.

Methods of job site preparation and decontamination chamber set-up, biodegradable foam and procedures, and removal methods; respiratory procedures; procedures for decontaminating the objects in the removal work procedures sections, methods of handling removed material and disposal procedures; cleanup procedures and equipment; signs and labels; fire exists and emergency procedures.

5. Contractor’s plan for 24 hour job security both for prevention of theft and for barring entry of curious but unprotected personnel into Work Areas.

6. Temporary utilities.

7. Documentation of compliance with environmental laws and standards.

1.15 STANDARD OPERATING PROCEDURES

A. Develop and implement a written standard procedure for abatement work to ensure maximum protection and safeguard from asbestos exposure of the workers, the non work areas of the school, visitors, employees, public, and environment.

B. The standard operating procedure shall ensure:

02082-22

CITY_21 MCI 00_014563795

NYC-WTC_000454595

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000454595Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →