SECTION 02082
asbestos waste has been placed prior to removal from the Work Area.
67. Structural Member: Eoad-supporting member of a facility, such as beams and
load-supporting walls, or any nonload-supporting member, such as ceiling and
nonload- supporting walls.
68. Surfactant: Chemical wetting agent added to water to improve penetration.
69. Visible Emissions: Emissions containing particulate material that are visually
detectable without the aid of instruments.
70. Washroom: Room between the Work Area and the holding area in the equipment
decontamination enclosure system where equipment and waste containers are wet
cleaned and/or HEPA-vacuumed prior to disposal.
71. Wet Cleaning: Removal of asbestos fibers from building surfaces and objects by
using cloths, mops, or other cleaning tools which have been dampened with
amended water.
72. Work Area: Designated rooms, spaces, or areas of the building or structure where
asbestos abatement activities take(s) place.
73. Worker Decontamination Enclosure System: Portion of a decontamination
enclosure system designed for controlled passage of workers and authorized
visitors, consisting of a clean room, a shower room, and an equipment room
separated from each other and from the Work Area by airlocks and curtained
doorways.
74. Work Site: Premises where abatement activity is being performed. May be
composed of one or more Work Areas.
1.14 SPECIAL PRECAUTIONS
A. The abatement project shall require a detailed plan of action to be prepared by the
Abatement Contractor for acceptance by the Construction Manager prior to
commencement of work.
The developed detail plan of action shall contain special preparation, removal and
cleanup techniques. The purpose of these special techniques is to intercept removed
asbestos containing materials before they settle in nooks and crannies and become
difficult to clean.
The detailed plan of action shall also include location(s) of asbestos control area(s),
decontamination chamber(s), sequencing of asbestos related work, disposal plan, type of
foam and asbestos sealer to be used, air monitoring and a detailed description of the
method to be employed in order to control pollution, including but not limited to
emergency procedures for fire and medical emergencies and for failure of seals. This
plan must be approved by the Construction Manager prior to the start of any asbestos
02082-21