Asbestos Abatement Technical Specifications
For 130 Cedar Street, New York, NY
2.58 Removal: The stripping of any ACM from surfaces or asbestos components of
a facility.
2.59 Renovation: Renovation shall mean an addition, alteration, change or
modification of the service equipment of a building that is not classified as an
ordinary repair as defined in 27-125 of the Administrative Code of the City of
New York.
2.60 Respiratory Protection Standard: Respiratory protection provided to workers
in accordance with Personnel Protection Equipment Requirements (OSHA 20
CFR 1926.58)
2.61 Shift: A workers', or simultaneous group of workers', complete daily term of
work. `
2.62 Shower Room: A room between the dean room and the equipment room in
the worker decontamination enclosure with hot and cold running water
controllable at a tap and arranged for complete showering during
decontamination.
2.63 Staging Area: The area near the waste transfer air lock where containerized
asbestos waste has been placed prior to removal from the work area.
2.64 Strip: To remove friable asbestos from any part of the facility.
• 2.65 Structural Member. Any load-supporting member of a facility, such as beams
and load-supporting walls, or any non-load-supporting member, such as
ceiling and non-load-supporting walls.
2.66 Surfactant A chemical wetting agent added to water to improve penetration.
2.67 Visible Emissions: Any emissions containing particulate asbestos material that
are visually detectable without the aid of instruments.
2.68 Washrooms: A room between the work area and the holding area in the
equipment DES where equipment and waste containers are wet cleaned
and/or HEPA vacuumed prior to disposal.
2.69 Waste Decontamination Enclosure System: The DES designated for the
controlled transfer of materials and equipment, consisting of a washroom and
a holding area.
2.70 Wet Cleaning: The removal of asbestos fibers from building surfaces
and objects by using cloths, mops or other cleaning tools that have been
dampened with water.
2.71 Work Area: Designated rooms, spaces or areas of the project where
asbestos abatement activities take place.
2.72 Work Site: Premises where asbestos abatement activity is taking place and
that may be comprised of one or more work areas.
Prepared by JLC Environmental Consultants, Inc. Project No. 04-3271 Page 13