ALLOWANCE FOR INCIDENTAL ASBESTOS ABATEMENT
Work as directed in the Work Order Letter and as required by these
Specifications. The Contractor is responsible to prepare and submit all filings,
notifications, etc. required by all City, State and Federal regulatory agencies
having jurisdiction.
The Contractor is responsible for amending the Asbestos Inspection Report
(ACP-7) Form initially submitted by DDC to the Department of Buildings and
resubmitting it to the Department of Environmental Protection, Asbestos Control
Program prior to abatement work as per Title 15, Chapter I of RCNY.
If more than one year has elapsed since the original ACP-7 was submitted to the
Department of Buildings, the Contractor is responsible for preparing and
submitting a new ACP-7 to the Department of Environmental Protection as well
as providing all other notifications to venous regulatory agencies as required.
In addition, The Contractor is also responsible for preparing, amending and
submitting Asbestos Variance Application (ACP-9) that may be required for the
completion of the Contract or incidental work.
The Contractor will be required to attend an on-site job meeting with the Resident
Engineer prior to the start of work to examine conditions and plan the sequence of
operations, etc.
I. All work shall be done during regular working hours unless the Contractor
requests authorization to work in other then regular working hours and such
authorization is granted by the Commissioner. (Regular work hours are those
hours during which any given facility, in which work is to be done, is customarily
open and functioning, normally between the hours of 8:00 A.M. and 4:00 P.M.
Monday - Friday.) If such work schedule is authorized by the Commissioner, the
work shall be done at no additional cost to the City.
J. The Commissioner may order that work be done in other than regular working
hours as hereinby defined and this order may require the Contractor to pay
premium or overtime wages to complete the work. If the Commissioner orders
work in other than regular working hours, the Contractor shall multiply the unit
price for that portion of the work requiring premium wages by 1.50 when
computing payment in accordance with Paragraph 1.08. All requests for premium
payment must be supported by certified payroll sheets and field sheets approved
by the Resident Engineer.
O Qualifications of Contractor
A. PRIOR PROJECT EXPERIENCE
1. The Contractor or Subcontractor performing the asbestos work specified
within this Section must have been in the business of performing asbestos
abatement work for a period of three years prior to the bid opening.
CAPITAL PROJECT NUMBER XXXXX 01020-93