Asbestos Abatement
C. Prepare to administer first aid to injured personnel after decontamination.
Seriously injured personnel shall be treated immediately or evacuated
immediately for decontamination. When an injury occurs, precautions shall be
taken to reduce airborne fiber concentrations (i.e. misting of the air with water)
until the injured person has been removed from the Work Area.
D. Notify, before actual removal of the asbestos material, the local police and fire
departments to the danger of entering the Work Area. Contractor shall make every
effort to help these agencies form plans of action should their personnel need to
enter the contaminated area.
1^ SUBMITTALS
A. Pre-Construction Submittals
1. Attend a pre-construction meeting scheduled by the City of New
York Department of Design and Construction. This meeting shall
also be attended by designated representative of the City of New
York third party air monitoring firm, facility manager and the
Resident Engineer. At this meeting, the Contractor shall present
three copies of the following items, bound and indexed. The
detailed plan of action must be submitted at least five (5) days prior
to the pre-construction meeting.
a. Contractor's scope of work, work plan and schedule.
b. Notifications to Government Agencies.
c. Copies of Permits, clearance and licenses if required.
d. Schedules: the Contractor shall provide to the Resident Engineer a
copy of the following schedules for approval. Once approved,
schedules shall be maintained and updated as received. Contractor
shall post a copy of all schedules at the site:
(1) A consti-uction schedule stating critical dates of the project
including, but not limited to, mobilization. Work Area
preparation, demolition, gross removal, fine cleaning,
encapsulation, inspections, clearance monitoring, and phase
of refinishing and final inspections. The schedule shall be
updated biweekly, at a minimum.
(2) A schedule of staffing stating number of workers per shift
per activity, name and number of supervisor(s) per shift,
shifts per day, and total days to be worked.
CAPITAL PROJECT NUMBER PO79201K 02081-23
100: CONTRACT DOCUMENTS REV. May 3,2000
- 23 -100% CONTRACT DOCUMENTS