SECTION 02082
protect, inform and warn people of the hazard from asbestos exposure. Post in a
prominent and convenient place for the workers a copy of the latest applicable
regulations from OSHA, EPA, NIOSH, State of New York and New York City and any
additional items mandated for posting by the aforementioned regulations.
D. Eumish all permits, variances and notices required to perform the Work.
1.18 EMERGENCY PRECAUTIONS
A. Establish emergency and fire exits from the Work Area. The clean side of all emergency
exits shall be equipped with two full sets of protective clothing and respirators at all
times.
B. Notify local medical emergency personnel, both ambulance crews and hospital
emergency room staff prior to commencement of abatement operations as to the
possibility of having to handle contaminated or injured workmen, and shall be advised on
safe decontamination.
C. Prepare to administer first aid to injured personnel after decontamination. Seriously
injured personnel shall be treated immediately or evacuated immediately for
decontamination. When an injury occurs, precautions shall be taken to reduce airborne
fiber concentrations (i.e. misting of the air with water) until the injured person has been
removed from the Work Area.
D. Notify, before actual removal of the asbestos material, the local police and fire
departments to the danger of entering the Work Area. Contractor shall make every effort
to help these agencies form plans of action should their personnel need to enter the
contaminated area.
1.19 SUBMITTALS
A. Pre-Construction Submittals
1. Attend a pre-construction meeting scheduled by the City of New York
Department of Design and Construction. This meeting shall also be attended by
designated representative of the third party air monitoring firm (Contractor’s and
Construction Manager’s air testing entity); facility manager. Construction
Manager and the Resident Engineer. At this meeting, the Contractor shall present
three copies of the following items, bound and indexed. The detailed plan of
action must be submitted at least five (5) days prior to the pre-construction
meeting.
a. Contractor’s scope of work, work plan and schedule.
b. Notifications to Government Agencies.
c. Copies of Permits, clearance and licenses if required.
02082-26
CITY_21 MCI 00_014563799
NYC-WTC_000454599