Asbestos Abatement
2. Smoke tubes shall be used to test the integrity of the Work Area barriers
and the decontamination enclosure systems daily before abatement
activity begins and at the end of each shift.
3. Damage and defects in the decontamination enclosure system shall be
repaired immediately upon discovery.
4. At any time during the abatement activity, if visible emissions are
observed, or elevated asbestos fiber counts outside the Work Area are
measured, or if damage occurs to barriers, abatement shall stop. The
source of the contamination shall be located, the integrity of the barriers
shall be restored and extended to include the contaminated area, and
visible residue shall be cleaned up using appropriate HEPA-vacuuming
and wet cleaning.
5. Inspections and observations shall be documented in the daily project log
by the asbestos handler supervisor.
3.6 MODIFICATIONS TO HVAC SYSTEMS
A. Shut down, isolated or seal, all existing HVAC units, fans, exhaust fans, perimeter
convection air units, supply and/or return air ducts, etc., situated in, traversing or
servicing the work zone.
B. Seal all seams with duct tap. Wrap entire duct with a minimum of two layers of 6
mil polyethylene sheeting. All shutdowns are to be coordinated with the Facility.
Where systems must be maintained, i.e. traversing Work Areas to non-Work
Areas, only supply ducts will be maintained, protect as described above. All
returns must be blanked off in Work Area and adjacent areas, including floor
above and below Work Area. When required Contractor shall apply for a
clarification from NYCDEP. The Contractor shall implement the following
engineering procedures:
1. Maintenance of a positive pressure within the HVAC system of 0.01 inch
water gauge (or greater) with respect to the ambient pressure outside the
Work Area. The conditions for this system shall be maintained and be
operational 24 hours per day from the initiation of Work Area preparation
until successful final air clearance;
2. The positive pressurization of the duct shall be tested, inspected and
recorded both at the beginning and at the end of each shift;
3. The positive pressurization shall be monitored using instrumentation
which will provide a written record of pressurization and that will trigger
an audible alarm, if the static pressure falls below the set value;
CAPITAL PROJECT NUMBER PO79201K 02081-61
100: CONTRACT DOCUMENTS REV. May 3,2000
-61 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631310
NYC-WTC_000416822