Asbestos Abatement
(2) Clean Room: The clean room shall share a common airlock
with the shower room and shall have a curtained doorway
to separate it from outside non-contaminated areas.
Lockers, for storage of workers' street clothing, and
shelves, for storing respirators, shall be provided in this
area. Clean disposable clothing, replacement filters for
respirators, and clean dry towels shall be provided in the
clean room. The clean room shall not used for the storage
of tool, equipment or other materials.
C. Decontamination Enclosure System Utilities: Lighting, heat, and electricity shall
be provided as necessary by the Contractor, and as specified herein.
3.2 Waste Decontamination FACILITY
A. Large Asbestos Project (Small Project Option)
1. Provide a worker decontamination facility in accordance with, Title 15,
Chapter 1, OSHA Standard 29 CFR 1926.1101, 12NYCRR Part 56 and as
specified herein. Unless approved by NYCDEP and the City, worker
decontamination facilities shall be attached to the Work Areas
a) Structure:
(1) Use modular systems or build using wood or metal frame
studs, joists, and rafters placed at a maximum of 16 inches
on-center.
(2) When worker decontamination unit is located outdoors, in
areas with public access, or in correctional facilities, frame
work shall be lined with minimum 3/8" thickness plywood
sheathing. Sheathing shall be caulked or taped airtight at all
joints and seams.
(3) Interior shall be covered with two layers of opaque 6-mil
polyethylene sheeting, with a minimum overlap of 16
inches at seams. Seal seams airtight using tape and
adhesive. The interior floor shall be covered with two (2)
layers of reinforced fire-retardant polyethylene sheeting
with a minimum overlap on the walls of sixteen inches.
(4) Entrances to the decontamination unit shall be secured with
lockable hinged doors. Doors shall be open at all times
when abatement operations are in progress. Doors shall be
louvered to allow for air movement through the
decontamination units into Work Area.
CAPITAL PROJECT NUMBER PO79201K 02081-58
100: CONTRACT DOCUMENTS REV. May 3,2000
- 58 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631307
NYC-WTC_000416819
OCR can misread numbers and units. Confirm readings against the page image before using them.