Asbestos Abatement
4. Turn off the pump and then the fan(s) when sampling is completed.
5. Collect a minimum number of area samples inside and outside each
homogeneous work area (5 inside/5 outside samples for Large Projects
and 3 inside/3 outside samples for Small Projects). In addition to the
minimum for Large Projects, one representative area samples shall be
collected inside and outside the work area for every 5,000 square feet
above 25,000 square feet of floor space where ACM has been abated.
P. For post-abatement monitoring, area samples shall conform to the following
schedule:
Area Samples
for Analysis by Minimum Volume Flow Rate
PCM 1,800 liters 5 to 15 liters/minute
TEM 1,250 liters 1 to 10 liters/minute
1. Each homogeneous work area that does not meet the clearance criteria
shall be thoroughly recleaned using wet methods, with the negative
pressure ventilation system in operation. New samples shall be collected
in the work area as described above. The process shall be repeated until
the work site meets the clearance criteria.
2. For an asbestos project with more than one homogeneous work area, the
release criterion shall be applied independently to each work area.
3. Should airborne fiber concentrations exceed the clearance criteria, the
Contractor shall reclean the work area utilizing wet wiping and HEPA-
vacuuming techniques. Following completion of recleaning activities, the
Testing Eaboratory will perform an obsei-vation of the Work Area. If the
Testing Laboratory determines that the work was performed in accordance
with the specifications, the appropriate settling period will be observed
and additional air sampling will be performed.
4. All costs resulting from additional air tests and observations shall be borne
by the Contractor. These costs may include, but are not limited to, labor,
analysis fees, materials, and expenses.
5. After the area has been found to be in compliance, the Contractor may
remove Isolation Barriers and perform final cleaning as specified.
Q. Clearance and/or Reoccupancy Criteria
1. The clearance criteria shall be applied to each homogeneous work area
independently.
CAPITAL PROJECT NUMBER PO79201K 02081-45
100: CONTRACT DOCUMENTS REV. May 3,2000
- 45 -100% CONTRACT DOCUMENTS