NYC 9/11 Public Portal Document
ALLOWANCE FOR INCIDENTAL ASBESTOS ABATEMENT
install and maintain any needed equipment to meet these requirements at his own
expense.
C. Electricity
The Department of Design and Construction will furnish all electricity needed for
construction, at no cost to the Contractor in a building, under their jurisdiction.
The Contractor is responsible for routing the electric power to the abatement
Work Area.
All temporaiy lighting and temporaiy electrical service for Work Area shall be in
weatherproof enclosures and be ground fault protected.
D. In leased spaces, arrangements for water supplies and electricity must be made
with the landlord. However, all such arrangements must be made through and are
subject to approval of the Department of Design and Construction. Utilities will
be provided at no cost to the Contractor. However, it is the Contractor's (or the
(General Contractor's) responsibility to furnish and install a suitable distribution
system to the Work Area. This system wild be provided at no cost to the City.
1.15 FEES
The Contractor shall be responsible for any and all fees or charges imposed
by Local, State or Federal Law, Rule and Regulation applicable to the work
specified herein, including fees or charges which may be imposed subsequent
to the date of the Bid opening.
PART 2 -PRODUCTS
Not used.
PART 3 - EXECUTION
Not used.
END OF SECTION
CAPITAL PROJECT NUMBER XXXXX 01020-1 03