Abatement specifications, exterior sealants, P.S. 92M

Machine-extracted title · confidence 45%

CoC/documents for asbestos-containing exterior sealant/caulking materials for DDC school task force, June 2001.

NYC-WTC_000455928–000456011
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

SECTION 02082 7. Electrical Power Cords: Use only grounded extension cords; use hard service cords where exposed to traffic and abrasion. Use single lengths of cords only.

8. Temporary Lighting: All lighting within the Work Area shall be liquid and moisture proof and designed for the use intended.

a) Provide sufficient temporary lighting to ensure proper workmanship everywhere; by combined use of daylight, general lighting, and portable plug­ in task lighting.

b) Provide lighting in the Decontamination Unit as required to supply a minimum 50-foot candle light level.

R. Telephone Paging Device:

1. Contractor or his authorized representative shall, at all times during the normal workday or during periods of overtime work under this Contract, carry a digital telephone paging device (Beeper). The device shall be activated by a telephone number in the 718, 212, 646, 917, 800, or 888 area codes. Contractor shall supply the City with the activation number for the device and respond to calls from City within one hour. The cost to Contractor for this device and all charges accruing thereto is deemed included in the Bid.

2.04 CLEANING

A. Throughout the construction period, the Contractor shall maintain that the building as described in this Section.

1. The Contractor shall prevent building areas other than the Work Area from becoming contaminated with asbestos-containing dust or debris. Should areas outside the Work Area become contaminated with asbestos-containing dust or debris as a consequence of the Contractor’s work practices, the Contractor shall be responsible for cleaning these areas in accordance with the procedures appended in Title 15, Chapter 1 of RCNY and NYSDOL ICR56. All costs incurred in cleaning or otherwise decontaminating non-Work Areas and the contents thereof shall be borne by the Contractor at no additional cost to the City.

2. The Contractor shall provide to all personnel and laborers the required equipment and materials needed to maintain the specified standard of cleanliness.

B. General

1. Waste water from asbestos removal operations, including shower water, may be discharged into the public sewer system only after approved filtration is on operation to remove asbestos fibers.

2. Asbestos wastes shall be double bagged in six mil (.006”) polyethylene bags approved for ACM disposal and shall be properly labeled and handled before disposal.

02082-59

CITY_21 MCI 00_014563915

NYC-WTC_000455986

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000455986Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →