ALLOWANCE FOR INCIDENTAL ASBESTOS ABATEMENT
opening regardless of size or configuration. This cost includes labor, consumable
materials, set-up/breakdown, removal and disposal, as required.
Note 1 : CREDIT: For items listed in A through F at a rate of 0.33 times the unit
price, times the respective multiple (for each item) will be taken for each
square foot of insulation which the Contractor is directed not to reapply
in above items.
Note 2: MINIMUM PAYMENT: The minimum payment per call at any
individual job sites or various job sites during the same day will be
five hundred dollars($500.00).
Note 3: Payment will be made as described in Paragraph 1.06 herein
Note 4: Provisions are made in this Contract to compensate the Contractor for
work performed in locations that are difficult to access due to work at
elevations that are significantly higher than the normal work level. The
unit price for these items will be paid at 1.20 times the unit price
described in Paragraphs 1.08 A. through R for those portions of the work
that are more than twelve (12) feet above the grade for that would be
judged as the normal working level.
1.9 GUARANTEE
A. Work performed in compliance with each Work Order Letter shall be guaranteed
for a period of one year from the date the completed work is accepted by the
Department of Design and Construction.
B. The Contractor shall not be held liable for the guarantee where the repair required
under the guarantee is a result of obvious abuse or vandalism as determined by
the Commissioner.
C. The Commissioner of The Department of Design and Construction will notify the
Contractor in writing regarding defects in work under the guarantee.
1.10 WORK BY OTHERS
A. The Department of Design and Construction reserves the right during the term of
this Contract to have work performed on asbestos abatement projects by other
Contractors and/or their own shop mechanics as warranted by field or project
conditions.
1.11 OCCUPANCY OF SITE NOT EXCLUSIVE
A. Attention is specifically drawn to the fact that Contractors, performing the work
of other Contracts, may be brought upon any of the work sites of this Contract.
Therefore, the Contractor shall not have exclusive rights to any site of his work
and shall fully cooperate and coordinate his work with the work of other
CAPITAL PROJECT NUMBER XXXXX 01020-101
100% CONTRACT DOCUMENTS REV. 0: DATE
CITY_21MC100_0 06631350
NYC-WTC_000416862