Asbestos Inspection Report
Premise No. Inspection Date:
130 Liberty Street 02/03/09
Floor Zip Borough (Block Lot Squad # Badge #
yarious_________ 10006 I1 I 54 1 1 A062
Inspector Building Type Basis of Inspection Photos Taken
M.Gagnidze F TRU2068MN08 yes
Contractor’s Name Sample Number
LVI Environmental
Address City Sample Number
State Zip Phone Sample Number
Laboratory Name Owner’s Name
TRC Environmental Corp The Lower Manhattan Development Corp.
Address City Address City
1340 Broadway New York One Liberty Plaza New York
State Zip Phone State Zip Phone
NY 10018 NY 1 Rw6 (212) 962-2300
Contact Person Time of Inspection from:
Arnel Javal, Sr. Proj. Mgr/TRC Environmental 5:45 pm to 6:45 pm
I arrived at the premise at 5:45 pm. LVI schedule informed that activities include demo ducts,
cut metal on 3™ and 2"'’ floors, clear off floor for demo on 1 ” floor.
I proceeded to the decon, signed the log book, don the appropriate level of personal protective
equipment to enter the regulated area on V floor, Negative air pressure on the floor was 0.023.
Three workers were present for the decon maintenance, cleaning the clean room and shower chamber.
Using B stairwell I proceeded to the 3^'’floor.
3’'“ Floor - 8 workers were working on the floor at the south side of the work area, cutting metal duct
with the power tool attached to the HEPA vacuum, picking up debris, placing into the boxes and spraying
with amended water, elevating electrical cables, preparing and wrapping boxes. A large
amount of poly wrapped beams exists on the floor. 8 Gaylord boxes were ready for load out.
Inspection was done on micro trap machines and tents.
I used B stairwell to proceed to the 2"^ floor.
2"'’ Floor - 20 workers were found inside the work place. Workers on scaffolds were removing the metal
fixtures from the ceiling, cutting air ducts into the pieces at the various locations of the floor, picking up
debris from the floor, placing into the boxes and spraying. Others were wrapping beams with poly,
preparing boxes. I observed that three light bulbs were hanging with open light protections.
I took the pictures and advised Handler Supervisor, who contacted electricians for emergency repair.
18 Gaylord boxes and a large amount of poly wrapped beams were ready to be taken out.
Inspection was done on micro trap machines and tents.
I used B stairwell to proceed to the Y* floor.
V’ Floor - 20 workers were clearing off the floor. A large amount of debris exists on the floor. Workers at
the shaft areas working to clear the shafts from debris at the different locations on the floor, placing debris
into the boxes, spraying boxes and work areas with amended water, sealing the critical barriers on the east
side, preparing, wrapping and loading out boxes through the waste decon, preparing the work area for
demolition. 20 open and sealed Gaylord boxes were on the floor. Inspection was done on micro trap
machines and tents.
After following the decontamination procedure I signed the log book and left the remote decon,
located on the ground floor.
Inspection was done on ATC trailer.
NOV# Infraction Infraction Infraction Infraction
NOV# Infraction Infraction Infraction Result Code
2
NOV# Infraction Infraction Infraction Supervisor's Initial
________
Borough l=Manhattan 2=Bronx 3=Brook,lyn 4=Queens 5=Richmond
Building Type A >6 stories B <6 stories C single family D school E hospital F public owned
Result Code I = Violation Issued 2=No Violation Issued 3=No access 4=Project not started (no NOV)
5-Public Owned Property'
CITY_DEP_WORBY_CANNATA_SUBP_000131231