NYC 9/11 Public Portal Document
Asbestos Inspection Report
Premise No. Inspection Date;
130 Liberty Street 03/09/09
Floor Zip Borough Block i Lot Squad # Badge #
Various_________ 10006 1 54 I 1 1 A062
Inspector Building Type Basis of Inspection Photos Taken
M Gagnidze F TRU2068MN08 yes
Contractor's Name Sample Number
LVI Environmental
Address City Sample Number
State Zip Phone Sample Number
Laboratory Name Owner’s Name
TRC Environmental Corp The Lower Manhattan Development Corp.
Address City Address City
1340 Broadway New York One Liberty Plaza New York
State Zip Phone State Zip Phone
NY 10018 NY TiTifi!6 (212)962-2300
Contact Person Time of Inspection from:
A me I Javal, Sr. Proj. Mgr/TRC Environmental 5:30 pm to 6:30 pm
I arrived at the premise at 5:30 pm. LVI schedule informed that activities include:
clear floor, cut ducts, demo walls, ceilings on V* floor.
I proceeded to the decon, signed the log book, don the appropriate level of personal
protective equipment to enter the regulated area on 1'floor. Three workers were present
for the decon maintenance, cleaning the shower chamber and organizing the clean room.
Negative air pressure manometer reading was -0.027.
V* Floor - 50 workers were present at the work area. At the east side vestibule I observed
six workers harnessed on two scissor lifts were breaking hard concrete ceiling into the pieces,
using hammer, and bringing down pieces from ceiling to the floor. One worker was spraying
the area with amended water. On the other side - west side of the area - three workers on
scissor lift were removing drop ceiling. The area has been also sprayed.
Two shaft areas were still full of debris and workers were clearing the openings, placing debris
into the boxes and spraying with amended water. Workers at the various locations were
cutting metal into small pieces, placing into the boxes and spraying with amended water.
Other workers were: replacing filters, preparing boxes, wrapping beams with 6 mil poly,
loading out sealed and sprayed boxes through the north side waste decon. A large amount of
debris and poly wrapped beams still exists on the floor.
75 Gaylord boxes were on the floor ready to be taken out.
35 micro trap machines were powered on and 5 on stand by. Inspection was done on micro trap tents.
I observed that there was an opening on poly right next to the tent 5 at the east side area
I advised Handler Supervisor to re-seal the hole.
After following the decontamination procedure I signed the log book and left the decon.
Inspection was done on ATC trailer.
NOV# Infraction Infraction Infraction Infraction
NOV# Infraction Infraction Infraction Result Code
2
NOV# Infraction Infraction Infraction Supervisor’s Initial
Borough I-Manhattan 2=Bronx 3=Brooklyn 4=Queens 5=Richmond
Building Type A >6 stories B <6 stories C single family D school E hospital F public owned
Result Code I = Violation Issued 2=No Violation Issued 3=No access 4=Projecl not started (no NOV)
3=Public Owned Property
C ITY_D EP_WO RBY_C AN NAT A SU B POO0131150
NYC-WTC_000182005