Asbestos Inspection Report
Premises: Inspection Date:
130 Liberty Street 06/24/09
Floor Zip Borough Block Lot Squad # Badge # AO11
Various________ 10006 1 54 1 1
Inspector Building Type Basis of Inspection Photos Taken
N. Patel A TRU2068MN08 Yes
Contractor’s Name Sample Number
LVI Environmental
Address City Sample Number
462 Getty Avenue Clifton
State Zip Phone Sample Number
NJ 07011 (973) 772-3660
Laboratory Name Owner’s Name
TRC Environmental corp. The Lower Manhattan Development Corp.
Address City , Address City
1430 Broadway New York One Liberty Plaza New York
State Zip Phone State Zip Phone
NY 10018 NY 10006 (212) 962-2300
Contact Person Time of Inspection from:
Arnel Javal, Sr. Proj. Mgr. / TRC Environmental 9:00 am - 9:40 am (1^’ floor & basement) and
1:30 pm -2:15 pm (1^‘floor& basement).
Inspection # 1
On the 1“ floor, I entered to the containment with PPE and met Mr. Luis Moya, Asbestos supervisor. There were
38 workers working on the floor. They were scrapping fireproofing in the shaft area, spraying amended water on
the brick wall and debris and boxing it, Jack hammering around columns floor in the S/E comer with HEPA
attached to it, preparing Gaylord boxes, cleaning water from the floor and in the decontamination system. Sixty
five (65) Gaylord boxes piled on the floor ready to be load out. Two negative air pressure equipments were not
operating in the south side and without Air filters. I took photos and told supervisor to fix it. I used step to go to
basement.
In the basement, I met Mr. Jose Jimenez, asbestos supervisor. There were 35 workers working on the floor. They
were cutting ducts with HEPA attached to the power tool, spraying amended water and cleaning it from floor,
loading out boxes, demolishing near the entrance of the basement boxing it and preparing Gaylord boxes. Five
Gaylord boxes and number of poly wrapped beams were on the floor ready to be load out. I exited out after
decontaminating and signing the log book.
Inspection # 2
On the 1 “ floor, I entered to the work area with the PPE and met Mr. Geraldo, asbestos supervisor. There were
40 workers working on the floor. They were scrapping fireproofing in the shaft area, spraying amended water on
the debris and boxing it, preparing Gaylord boxes. Jack hammering the floor with HEPA attached to the power
tool and two workers pouring cement mixture into the trenches in the south side. I took the photos and advised
Handler Supervisor to stop all cement pouring activities. The cemenhconcrete issue was raised by EPA 10 days
ago on the 2”'* floor. Total 67 Gaylord boxes piled on the floor ready to be load out. Negative Air pressure was -
0.037.1 used steps to go to basement.
In the basement, I met Mr. Jorge Sandoval, foreman. There were 36 workers working on the floor. They were
cutting ducts with HEPA attached to the power tool, spraying amended water on the debris and boxing it,
cleaning water from the floor, loading out boxes and preparing Gaylord boxes. Twenty three (23) Gaylord boxes
and numerous poly wrapped beams piled on the floor ready to be load out. I proceeded to the decontamination
system, decontaminated myself, signed the log book and exited out. My observations were discussed with the
Mr. Gerry Nugent of LVI, Mr. Amel Javal of TRC and ATC personnel. LVI was instructed to foam only and not
to pour any cement in the work areas.
NOV# REoUlT
2
NOV#
NOV# SUHtKVISOK 7"
Borough l=Manhartan 2=Bronx 3=BrookJyn 4=Queens 5=RichmoQd
Building Type A >6 stones B <6 stories C single family D school E hospital F public owned
Result Code 1 = Violation Issued 2=No Violation Issued 3=No access 4=Project not started (no NOV) 5=Public Owned Property