Same-box records
Bulletin #1: Port Authority comments on MOEM work, undated · Box 7DCASNYC-WTC_000173279
A document listing Port Authority comments and associated cost adjustments for the Mayor's Office of Emergency Management renovation.
Same agency, volume and box · similarity 0.912
Bulletin #1 cost proposal for hurricane wall work, Sept 1998 · Box 7DCASNYC-WTC_000172039
Cost comparison sheet detailing labor and material estimates for hurricane wall modifications at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.901
Revised Change Order #004 for MOEM work, September 1998 · Box 7DCASNYC-WTC_000173274
A revised change order detailing scope changes and costs for the Mayor's Office of Emergency Management renovation project.
Same agency, volume and box · similarity 0.896
Revised Change Order #004, 7 World Trade Center, September 1998 · Box 7DCASNYC-WTC_000173458
Letter submitting a revised Change Order #004 for concrete and electrical work at 7 World Trade Center.
Same agency, volume and box · similarity 0.893
Revised change order #004, 7 World Trade Center, September 1998 · Box 7DCASNYC-WTC_000173175
Revised change order from Ambassador Construction Co. Inc. for concrete work and panel capacity changes at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.893
Revised Change Order #004 for MOEM work, September 1998 · Box 7DCASNYC-WTC_000173271
A revised change order detailing scope changes and costs for the Mayor's Office of Emergency Management renovation project.
Same agency, volume and box · similarity 0.892
Revised Change Order #4 Memo, 7 World Trade Center, Sept · Box 7DCASNYC-WTC_000168669
Memo submitting revised Change Order #004 for oil tank and electrical panel work at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.890
Bulletin #1 regarding Hurricane Wall work at 7 World Trade · Box 7DCASNYC-WTC_000173408
Bulletins detailing costs for hurricane wall construction, column reinforcement, and sheetrock installation at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.888
Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · Box 7DCASNYC-WTC_000172020
Cost comparison table for Hurricane Wall work items under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.
1 shared topics · Same agency, volume and box · similarity 0.885
Revised Change Order #004, Sept 1998 · Box 7DCASNYC-WTC_000173309
Letter from Ambassador Construction submitting a revised change order for work at 7 World Trade Center.
Same agency, volume and box · similarity 0.885
Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · Box 7DCASNYC-WTC_000172034
Cost comparison table for Hurricane Wall work items under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.
1 shared topics · Same agency, volume and box · similarity 0.884
Bulletin #1: Port Authority comments on MOEM work, undated · Box 7DCASNYC-WTC_000173277
A document listing Port Authority comments and associated cost adjustments for the Mayor's Office of Emergency Management renovation.
1 shared topics · Same agency, volume and box · similarity 0.884