AMBASSADOR CONSTRUCTION CO, INC.
JUN - 9 !998
June 9, 1998
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center
1st, 7th & 23rd Floors
Dear Mr. Weems:
We are in receipt of the response from the Division of Real Estate Service regarding the
above referenced project. The following is Ambassador's response;
ltem_NcLl
The cost representation in our estimate does not include Addenda 1. We did not have
sufficient time to include the addenda in our original estimate. The cost estimate for Addenda
1 will be submitted shortly.
Item No. 3
The rubbish removal cost of $35,100 will be removed. The cut and patch line item is not a
general conditions item, it .a valid.part Gf the work" —
■--‘'•^TferhNo.4 ~
Our cost estimate does not include the cost for the tenant’s use of the existing fuel lines. That
cost has been submitted separately by Silverstein.
Item No. 5
Ambassador’s line item for the Generator Test represents the cost for the Design Engineer to
go to the factory and test the generator as called for in the Specifications, page PPS-23 under
Factory Testing. The cost represents time, travel and meals for the engineer. The cost for
Generator Testing in the electric trade bid is the testing of the generator on the job site as
called for in the Specifications, page PPS-24 under Site Testing.
General Comment Exhibit “X”
Item No. 1
We will comply by supplying the additional bids requested.