Facsimile cover sheet from Ambassador Construction Co. Inc. dated June 11, 1999 regarding work at 7 World Trade Center.
Same agency, volume and box · similarity 0.946
machine-extracted · confidence unavailable · Check page ↗Contractor submission of change order #088 to install new fuel oil piping and relocate ductwork at 7 World Trade Center.
NYC-WTC_000171303–000171307Folder label: “Mayor's Office of Emergency Management 7 World Trade Center Change Order #088 Amb. Job #S57-5175”

OCR status: ocr · source: ours
NYC-WTC_000171307 EW 2 HR RATED FIREPROOFING NEW FUEL LINE - EXISTING STEEL BEAN W/ 4 HR FIRE PROOFING •LIGHT AIX 08/18/88 08:32 FAT_2122190256 „S-.SL PUSH-UP FIRE DOOR BY COOKSON MODEL #FD-1 OR EQUAL (3HR FIRE RATED) TIE-IN TO BLDG. FIRE ALARM SYSTEM MEA #114-90-M CLASS "A" FIRE DOOR FUEL STORAGE TANK -4" HIGH : OIL PROO ACCESS t „{-,SZ .0,1 SWANKE HAYDEN CONNELL LIGHT FIX .01-6 •NEW STRUCTURE & 4HR FIRE PROOFING g" CONC BLOCK WALL SECTION - FUEL OIL TANK RM 20' LIMIT HT. # (4) 16" o.c. MAX. VEF W/ HORIZONTAL MASONRY REINFORCING @004/004 NYC 9/11 Public Portal Document
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000171743
Facsimile cover sheet from Ambassador Construction Co. Inc. dated June 11, 1999 regarding work at 7 World Trade Center.
Same agency, volume and box · similarity 0.946
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168409
Contractor submits Change Order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at the Mayor's Office of Emergency Management.
2 shared non-person entities · Same agency, volume and box · similarity 0.945
machine-extracted · confidence unavailable · Check page ↗3 shared non-person entities · Same agency, volume and box · similarity 0.937
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168439
Change order for $85,893 covering support structures, concrete encasement, routing, and patching for fuel oil lines and enclosures at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.918
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171313
Letter detailing required additional welds and pipe length for a new fuel line route at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.918
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171739
Letter submitting change order costs for fuel line work at the Mayor's Office of Emergency Management.
2 shared non-person entities · Same agency, volume and box · similarity 0.916
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171318
Contractor submission of revised change order #44R for fuel oil line supports, enclosures, and new routing at 7 World Trade Center.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.912
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173453
Letter from Ambassador Construction submitting Change Order #004 for concrete and electrical work at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.910
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172028
Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.909
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168407
Letter submitting change order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at 7 World Trade Center.
3 shared non-person entities · Same agency, volume and box · similarity 0.907
machine-extracted · confidence unavailable · Check page ↗1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.904
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000172231
Submission of Change Order #85 for $34,401 for additional work related to fuel-oil line routing at 7 World Trade Center.
2 shared non-person entities · Same agency, volume and box · similarity 0.904
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Contractor submits Change Order #88 for $120,957 to install an eight-inch conduit for fuel oil piping at the Mayor's Office of Emergency Management.
Filed in the same folder
NYC-WTC_000171743
Facsimile cover sheet from Ambassador Construction Co. Inc. dated June 11, 1999 regarding work at 7 World Trade Center.
Similar indexed content
Similar indexed content
NYC-WTC_000168439
Change order for $85,893 covering support structures, concrete encasement, routing, and patching for fuel oil lines and enclosures at 7 World Trade Center.
Similar indexed content
NYC-WTC_000171313
Letter detailing required additional welds and pipe length for a new fuel line route at 7 World Trade Center.
Similar indexed content