JON 26 ’99 16:17 PR OMBfiSSADOR CONSTR. C0212 949 9762 TO 7325190 P. 02/02
AMBASSADOR CONSTRUCTION CO, INC.
♦
January 26, 1999
Mr Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center
1, 7 & 23rd Floors
Change Order #060
Amb. Job # S57-5175
Dear Mr. Weems.
We are pleased to submit herewith our change order #060 to perform the following work at the
atxive referenced premises for the sum of EIGHT THOUSAND ONE HUNDRED FOURTEEN
DOLLARS ($8,114.00).
SCOPE OF WORK
As per Swanke Hayden Connell’s sketch FSK-54 to close gap at steel in hurricane wall with
16 gauge steel plate. The cost is as follows;
Labor 55,500.00
Material 1,500.00
Subtotal $7,000.00
General Conditions 560 00
Overhead & Fee 454 00
Insurance 100.00
Total $9,114.00
Please advise if you wish for us to proceed with this work.
Very tfuly yours.
< CO<STaUCT/)N , INC
Martin Schrlei^r
Vice President
MS’.ag
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted:_________ Dated:
C'\«paocs'ioe(n«ostoemco60 wpdl
317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762