JAN 26 ’.99, 16:20 PR AMBASSRDOR CONSTR. C0212 949 9762 TO 6693640 P.02^03
AMBASSADOR CONSTRUCTION'CQ, INC
♦
January 26,1999
Mr. Walter Weems
Silverstein Properties, InC.
7 World Trade Center
New York, NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center
1, 7 & 23rd Floors
Change Order #060
Amb.Job-#-£57-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #060 to perform the following work at the
above referenced premises for the sum of EIGHT THOUSAND ONE HUNDRED FOURTEEN
DOLLARS ($8,114.00);
SCOPE OF WORK
As per Swanke Hayden Connell's sketch FSK-54 to close gap at steel in hurricane wall with
16 gauge steel plate. The cost is as follows:
Labor $5,500.00
Material /LSQQJDO
Subtotal $7,000,00
General Conditions 560.00
Overhead & Fee 454.00
Insurance lOQjQO
Total $8,114.00
Please advise if you wish for us to proceed with this work.
Very tfOly yours,
F CO«ST^CTJ INC-
Martin Schrrei^r
Vice President
MS;ag
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted;_______ Dated:
c:Wipdocs\oeni\cosioemcoso.wpd]
317 MADISON AVENUE, NEW YORK. NY 10017,212 922 1020, FAX 212 949 9762