3. Material that has been removed because it is too wet to permit
compaction may be stockpiled or spread and allowed to dry. Assist
drying by discing, harrowing, or pulverizing, until moisture content is
reduced to a satisfactory value, as determined by moisture-density
relation test.
3.15 FIELD QUALITY CONTROL
A. Contractor's testing laboratory shall perform laboratory maximum density
tests for each material proposed for use in backfilling. Results of these
tests shall be submitted to the Engineer and may be used by the Engineer to
determine acceptability of materials and methods of compacting. Perform
sampling and testing, and submit test results in a timely manner to avoid
unnecessary delays in the work.
B. Field density tests will be performed by the Engineer. The Contractor shall
provide necessary cooperation and shall schedule his operations as required
to permit sampling and testing.
3.16 MAINTENANCE
A. Protect newly graded areas from unnecessary traffic and from erosion, and
keep free of trash and debris.
B. Repair and reestablish grades in settled, eroded, and rutted areas to
specified tolerances.
END OF SECTION
Contract 02220-14 Excavation and
1-02-21064-0-0 Backfilling
NYC-WTC_000165821
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000165821Source: NYC Law Department, mirrored locally