NYC 9/11 Public Portal Document
Gilsenan, Michael
From: Smyth, Virginia
Sent: Friday, February 21, 2003 2:42 PM
To: Radhakrishnan, Krish; Gilsenan, Michael
Subject: FW: Information needed for PW 882
The following are some additional questions from FEMA we need to address.
---- Original Message----
From: Asbill, Susan Annette [mailto:[email protected]]
Sent: Friday, February 21, 2003 11:05 AM
To: '[email protected]'
Subject: Information needed for PW 882
Virginia,
I wanted to check with you to see if you have a projected date of when the
following information will be available. FEMA is waiting on this
information to complete the version to PW 882.
1. HVAC
A. Sample of one of the contracts with a HVAC contractor
B. Cost estimate for cleaning a complete central HVAC system
2. Cleaning change order - In reviewing the cleaning change orders faxed to
FEMA, I have the following questions
A. Who makes the determination to remove the carpet from the common areas?
B. Is the carpet tested before removal?
C. How is DEP handling the apartment building's insurance proceeds?
D. How were the estimates derived for the cleaning of the apartments and
terraces above 2000 sq. feet?
3. Cleaning contractors call to residents the night before the cleaning
A. Revised contract scopes of work for the this task
B. Cost estimates if there are increased costs.
If you have any questions please do not hesitate to call me at 212-416-0351.
Best regards,
Annette Asbill